Skip to content

Construction, the 10% test, and getting to 8609 — California

Phase 10 of 11

"I have the allocation and I'm building. What has to be true, and by when, before CTCAC will issue the 8609?"

Not yet covered18–30 months (construction + lease-up), inside a fixed statutory placed-in-service deadline

The clocks you are now running against

This phase starts when the readiness submission is behind you and the calendar stops being about applications. Four dates govern it, and none of them are negotiable in the ordinary course.

The four dates that govern this phase
DeadlineTimingCitation
Start of construction (if maximum Readiness points were not claimed)Within 12 months of reservation; failure "may result in rescission"4 CCR § 10328(c)
10% test, documentation, and land ownershipWithin 12 months of the carryover allocation date§ 10328(d)
Placed in serviceBy the close of the second calendar year following the calendar year in which the allocation was madeIRC § 42(h)(1)(E)(i)
Placed-in-service packageWithin 1 year of the final certificate of occupancy — the latest CofO where there are multiple buildings§ 10322(i)(1)(A)

Note the unit of measure on the third one. The placed-in-service deadline is stated in calendar years, not elapsed months, so a December allocation reads like "two more years" and is really closer to 24 months minus whatever the readiness period already consumed. A January allocation on the same nominal rule buys nearly a year more runway. Schedule against the actual close-of-year date, not a mental 24-month bar.

14–24 months (unverified)Construction (CA garden/podium, 50–150 units)
3–9 months (unverified)To stabilized occupancy
6–18 months (unverified)Final CofO to 8609 issuance

The durations behind those figures are the weakest data in the whole domain — the research behind this guide could not verify any of them from a primary or published source, and labels them folklore. They are load-bearing for the placed-in-service deadline. Use your own completed-deal history, not the rules of thumb.

The 10% test: the arithmetic is easy, the inclusions are not

The statute is explicit: the taxpayer's basis in the project as of the date one year after the allocation was made must exceed 10 percent of reasonably expected basis as of the close of the second calendar year following the allocation year (IRC Section 42(h)(1)(E)(ii)). CTCAC applies the same 12 months and adds two conditions of its own — documentation and land ownership (Section 10328(d)).

There is an unresolved conflict here and it should be named rather than papered over. 26 CFR Section 1.42-6(a)(2)(i)–(ii) still says the test must be met by the close of the calendar year for allocations made before July 1, and within six months for allocations made after June 30. That text predates the 2008 HERA amendment that moved the test to a uniform 12 months, and no IRS notice reconciling the two was located. The statute and CTCAC both say 12 months, so 12 months governs — but the regulation's consequence rules are still operative.

Consequence of a missed test under the still-operative regulation
Allocation timingConsequenceCitation
Before July 1Allocation is invalid — treated as never made26 CFR § 1.42-6(a)(2)(i)
After June 30Must be returned; falls into the following year's returned-credit component§ 1.42-6(a)(2)(ii); § 1.42-14(d)(1)

What counts toward the numerator is broader than eligible basis in one direction and narrower in another.

What counts toward the 10% test numerator
ItemTreatmentCitation
Adjusted basis in land or depreciable property reasonably expected to be part of the projectCounts whether or not it is includible in eligible basis — so commercial space counts§ 1.42-6(b)(1)
Nonrefundable deposit or option paymentCounts if properly capitalizable§ 1.42-6(b)(2)(i)
QCT/DDA 130% eligible-basis boostDoes not count — counting it is one of the more common modeling errors in the phase§ 1.42-6(b)(2)(ii)
Payment and fee conditions for counting toward the numerator
RequirementConditionCitation
CostsMust actually be paid (cash method) or accrued (accrual method)§ 1.42-6(b)(2)(iii)
FeesCount only if reasonable, legally obligated, capitalizable, not paid to yourself, and — if paid to a related party on the cash method — properly accruable§ 1.42-6(b)(2)(iv)(A)–(E)

Most 10% test failures are not spending failures; they are documentation failures on costs that were genuinely incurred.

Verification is by taxpayer certification under penalty of perjury, or by an attorney or CPA certification, with agency review of supporting documentation (Section 1.42-6(c)(2)). The percentage is arithmetic. The signature is a professional liability product.

The bond track runs a parallel and partly different calendar

On a 4% deal the CDLAC clock does not stop at readiness. Unused allocation reverts to the Committee automatically at deadline expiry unless transferred or carried forward — no notice, no cure.

CDLAC bond-track deadlines, filings, and forfeitures
RequirementDeadline / thresholdCitation
Bond issuanceNo later than December 31 of the year following the allocation year, per the Committee ResolutionCDLAC § 5010(a)(1)–(2)
Unused allocation reversionAutomatic at deadline expiry, unless transferred or carried forward§ 5010(d)
Notify CDLAC of bond issuanceWithin 24 hours of issuing the bonds§ 5012(a)
Report of Action TakenWithin 15 calendar days of the first bond closing§ 5012(b)
Performance deposit forfeiturePro-rata forfeiture if less than 80% of the allocation is used to issue bonds; full refund at 80% or above§ 5006(c)
CTCAC development timetable update — rehabBy December 31 of the year following reservation4 CCR § 10326(j)(3)
CTCAC development timetable update — new constructionBy December 31 of the second year following reservation§ 10326(j)(3)
Placed-in-service package (bond deals)Same Section 10322(i) package as the 9% side§ 10326(k)
Acquisition/rehab qualifying expenditure windowWithin a 24-month period; must meet the greater of 20% of adjusted basis or $6,000 per low-income unit, inflation-indexed since 2009IRC § 42(e)(3)(A)(ii), (D)

Two federal traps are set much earlier and detonate here. Pre-inducement predevelopment spending quietly shrinks the numerator of the 25%/50% test, and bond counsel usually finds it at closing. A stale TEFRA means a re-hearing at the worst possible moment.

Federal bond timing traps
RequirementDeadlineCitation
Issuer's official intentAdopted no later than 60 days after payment of the original expenditure26 CFR § 1.150-2(d)(1)
Reimbursement allocationNo later than 18 months after the later of the expenditure date or the placed-in-service/abandonment date, and in no event more than 3 years after the expenditure§ 1.150-2(d)(2)(i)
TEFRA public approvalTimely only if obtained within 1 year before the issue date§ 1.147(f)-1(f)(7)
TEFRA hearing noticeNo fewer than 7 calendar days before the hearing§ 1.147(f)-1(d)(4)

Placing in service is a filing event, not a construction event

CTCAC issues Form 8609 / FTB 3521A only after three things exist: the placed-in-service package, the recorded regulatory agreement, and the compliance fee (Section 10322(i)). Certificates of occupancy alone get you nothing.

Requirements before 8609 issuance
RequirementDeadline / amountCitation
Placed-in-service packageDue within 1 year of the final certificate of occupancy§ 10322(i)(1)(A)
Permanent conversion documentsDue within 60 days of conversion, if conversion post-dates the package (added by the January 24, 2024 amendments)§ 10322(i)(1)(C)
Recorded CTCAC regulatory agreementMust be executed and recorded§ 10322(i)(2)
Compliance monitoring fee$700 per low-income unit — $70,000 on a 100-unit deal; a one-time capitalized charge covering monitoring throughout the extended-use period, routinely absent from early development budgets§ 10335(f)
Nonprofit right of first refusal (9% competitive, all-nonprofit GP deals)Must be demonstrated in the partnership agreement before 8609 issuance§ 10337(a)(3)

Then the federal step people forget. The owner must certify first-year information to the IRS following the close of the first taxable year of the credit period, and failure to certify means no credit is allowable for any taxable year ending before the certification is made (IRC Section 42(l)(1)). Failure to give CTCAC a copy of the completed 8609 showing that first-year filing is an enumerated negative-point item (Section 10325(c)(2)(K)).

Late filing of the placed-in-service package is itself an enumerated negative-point item (Section 10325(c)(2)(C)). It delays the 8609, which delays the investor's first-year credit, which delays the final equity installment. A clerical slip at the end of the phase costs real money at the closing table.

Lease-up decides the credit, permanently

Qualified basis and applicable fraction are recorded at the end of the first credit year (26 CFR Section 1.42-5(b)(1)(viii)). An unqualified household occupying a unit in year one permanently reduces the applicable fraction for all 15 years. This is a lease-up execution risk with a 15-year tail, and it is almost never modeled at feasibility stage.

Credit period and compliance period
ItemRuleCitation
Credit period10 taxable years, beginning with the year the building is placed in service or, by election, the following yearIRC § 42(f)(1)
Compliance period15 taxable years, beginning with the first taxable year of the credit period§ 42(i)(1)

The deferral election is a genuine lever when a building places in service late in a calendar year with thin occupancy.

Certification mechanics attach immediately.

100% affordable property certification mechanics
RequirementDetailCitation
Move-in certificationRequired, plus a first annual recertification4 CCR § 10337(b)(1)
Ongoing income verificationMay be discontinued after the first annual recertification§ 10337(b)(1)
Full-time student statusMust be checked for the entire tenancy and throughout the initial compliance period§ 10337(b)(1); IRC § 142(d)(3)(A)
RecordkeepingContinues§ 10337(b)(1)

"No recerts" is the wrong summary of that rule.

Two moving targets to check against your lease-up window.

Two rules moving under your lease-up window
ItemCurrent ruleSource
Move-in / recertification TIC signature windowNo longer required within 5 days of the TIC effective date — may be signed within 120 days of the effective dateCTCAC Compliance Policy Updates memo, July 9, 2026
HOTMA implementationOptional from January 1, 2024; mandatory January 1, 2027, with income and asset documentation collected within 120 days of that date. As of CTCAC's August 4, 2026 memo, the IRS had not released LIHTC-specific HOTMA guidanceCTCAC HOTMA Guidance memo, August 4, 2026

A building leasing up now crosses that boundary mid-portfolio.

Physical inspection and on-site monitoring
ItemRuleCitation
NSPIREHas applied since January 1, 20244 CCR § 10337(c)(4)(B)
InspectCheckApplies from September 1, 2026, exclusively in 2027CTCAC memo, July 9, 2026
First on-site monitoring visitBy the end of the second calendar year following the year the last building is placed in service, then every 3 years4 CCR § 10337(c)(4); 26 CFR § 1.42-5(c)(2)(iii)(A)

The file discipline you set during lease-up is the file discipline that gets audited.

Retention is longer than most operators assume.

Record retention
RecordsRetention periodCitation
Each year's records6 years after the due date of that year's federal return26 CFR § 1.42-5(b)(2)
Year-one credit-period file6 years beyond the due date of the return for the last year of the compliance period — roughly 21 years of custody4 CCR § 10337(c)(2)(A)

Missing a date, and the narrow ways out

Reservation Exchange — the only relief from the placed-in-service deadline (4 CCR § 10328(g))
Qualifying circumstance
High-Rise projects returning credit in January of the following year
Disaster-caused construction delay
FCAA-2020/CAA-2021 credit returned in January
Waiting List projects
Executive Director discretion for circumstances beyond the applicant's control

Anything outside that list is a total loss of the allocation.

Negative points are the mechanism that makes a single missed date a multi-year problem. They run up to 10 per project and/or per violation and are assessable against general partners, co-developers, management agents, consultants, guarantors and any Development Team member (Section 10325(c)(2)). CDLAC negative points are mirrored into CTCAC scoring and vice versa (Section 10325(c)(2)(T)). The penalty follows the sponsor into its next applications.

Performance deposit: refund vs. forfeiture (4 CCR § 10335(e))
OutcomeConditionsCitation
Full refundPlacing in service on time, qualifying under Section 42, meeting all reservation conditions, certifying the credits will be claimed, and executing the regulatory agreement§ 10335(e)(3)
Non-refundableCredits returned after acceptance — except for natural disaster, lawsuit, or similar extraordinary circumstance§ 10335(e)(2)

One more exposure spans the readiness-to-close window: pricing decay.

~3 monthsApplication to award
~6–12 monthsAward to construction close

CTCAC re-runs feasibility and cost reasonableness at the readiness submission (Sections 10325(c)(7), 10328(c)), and a materially changed financing plan "may cause the project to be reconsidered by the Committee." A deal that repriced hard between application and close is not just a budget problem — it is re-underwriting risk.

What the sources do not settle

Four things are genuinely open, and a schedule built on this phase should treat them as inputs rather than knowns.

No published distribution of real California LIHTC construction and lease-up durations exists. The 14–24 month construction, 3–9 month stabilization and 6–18 month CofO-to-8609 ranges circulating among practitioners could not be verified from a primary or published source. Joining CTCAC reservation dates to placed-in-service dates in the published project lists would produce a defensible empirical distribution — nobody has assembled it.

CTCAC's own processing time from placed-in-service package submission to 8609 issuance is not published. That gap sits directly between your final CofO and the investor's final equity installment.

The IRS has not, as far as this research could determine, formally reconciled 26 CFR Section 1.42-6(a)(2) with the post-HERA 12-month rule in IRC Section 42(h)(1)(E)(ii). CTCAC applies 12 months. Implement the statute, surface the conflict, and keep the regulation's consequence rules.

And LIHTC-specific HOTMA guidance from the IRS did not exist as of CTCAC's August 4, 2026 memo, with the mandatory implementation date of January 1, 2027 approaching. Buildings leasing up across that date are operating on a state agency's implementation schedule without federal program guidance.

Where this goes wrong

  • Counting the QCT/DDA 130% boost toward the 10% test. It is expressly excluded by 26 CFR Section 1.42-6(b)(2)(ii), and including it makes a failing project look like it cleared the bar.
  • Implementing the regulation's 10% test dates instead of the statute's. 26 CFR Section 1.42-6(a)(2) still carries the pre-HERA close-of-calendar-year and six-month deadlines; the statute and CTCAC both say 12 months.
  • Treating a December allocation as "two more years" to place in service. The deadline is close of the second calendar year after the allocation year, so a late-year allocation gets roughly 24 months minus whatever the readiness period consumed.
  • Costs paid but not documented as capitalizable, legally obligated, or properly accrued. Most 10% test failures are documentation failures on real spending, not shortfalls in spending (26 CFR Section 1.42-6(b)(2)(iii)–(iv)).
  • Predevelopment costs paid more than 60 days before the issuer's official intent resolution. They cannot be reimbursed from bond proceeds (26 CFR Section 1.150-2(d)(1)), shrinking the 25%/50% test numerator — and bond counsel usually catches it at closing.
  • Letting TEFRA approval go stale. It is timely only if obtained within one year before the issue date (26 CFR Section 1.147(f)-1(f)(7)); a re-hearing lands at the worst point in the schedule.
  • Letting the bond allocation lapse. It reverts to the Committee automatically at deadline expiry with no cure step (CDLAC Section 5010(d)), and under-issuing below 80% forfeits a pro-rata share of the performance deposit (Section 5006(c)).
  • Leasing an unqualified household into a unit in year one. Applicable fraction is fixed at the end of the first credit year (26 CFR Section 1.42-5(b)(1)(viii)) and the reduction runs for all 15 years.
  • Omitting the $700-per-low-income-unit compliance monitoring fee from the development budget. It is payable before 8609 issuance and is $70,000 on a 100-unit deal (Section 10335(f)).
  • Missing the IRC Section 42(l)(1) first-year certification. No credit is allowable for any taxable year ending before the certification is made — and failing to give CTCAC the completed 8609 is a separate negative-point item (Section 10325(c)(2)(K)).
  • Filing the placed-in-service package late. It is an enumerated negative-point item (Section 10325(c)(2)(C)) and it delays 8609, the investor's first-year credit, and the final equity installment.
  • Assuming a general hardship gets you past the placed-in-service deadline. Relief is limited to the enumerated Section 10328(g) Reservation Exchange list; everything else is a total loss of the allocation.
  • Reading the 100% affordable exemption as "no recertifications." Move-in plus a first annual recertification are still required, and full-time student status must be checked for the entire tenancy and throughout the initial compliance period (4 CCR Section 10337(b)(1)).

At a glance

10% test deadline
12 months from the carryover allocation date — also the deadline to own the land (4 CCR Section 10328(d); IRC Section 42(h)(1)(E)(ii))
Placed-in-service deadline
Close of the second calendar year following the allocation year (IRC Section 42(h)(1)(E)(i))
Start of construction (non-max-readiness)
12 months from reservation (Section 10328(c))
Placed-in-service package due
Within 1 year of the final certificate of occupancy (Section 10322(i)(1)(A))
Permanent conversion documents
Within 60 days of conversion if it post-dates the PIS package (Section 10322(i)(1)(C))
Compliance monitoring fee
$700 per low-income unit, payable before 8609 issuance — $70,000 on a 100-unit deal (Section 10335(f))
Bond issuance deadline
No later than December 31 of the year following the allocation year; unused allocation reverts automatically (CDLAC Sections 5010(a)(1)–(2), 5010(d))
Post-issuance filings
Notify CDLAC within 24 hours of issuance; Report of Action Taken within 15 calendar days of first closing (Sections 5012(a), 5012(b))
Bond deposit forfeiture threshold
Pro-rata forfeiture if less than 80% of the allocation is used to issue bonds (Section 5006(c))
Rehab expenditure window
24 months; greater of 20% of adjusted basis or $6,000 per low-income unit, inflation-indexed since 2009 (IRC Section 42(e)(3)(A)(ii), (D))
Negative points exposure
Up to 10 per project and/or per violation, assessable against GPs, co-developers, management agents, consultants, guarantors and any Development Team member (Section 10325(c)(2))
First on-site monitoring visit
By end of the second calendar year following the year the last building is placed in service, then every 3 years (4 CCR Section 10337(c)(4); 26 CFR Section 1.42-5(c)(2)(iii)(A))
Year-one file retention
6 years beyond the due date of the return for the last year of the compliance period — roughly 21 years (26 CFR Section 1.42-5(b)(2))
Construction + lease-up (unverified)
14–24 months construction, 3–9 months to stabilization, 6–18 months CofO to 8609 — practitioner folklore, not verified from any primary or published source

Governing authority

  • Placed-in-service deadlineIRC Section 42(h)(1)(E)(i)
  • 10% test — statutory ruleIRC Section 42(h)(1)(E)(ii)
  • 10% test — content and verification26 CFR Section 1.42-6(a)(2), (b), (c)(2)
  • Consequence of a missed 10% test26 CFR Sections 1.42-6(a)(2)(i)–(ii), 1.42-14(d)(1)
  • Credit period and compliance periodIRC Sections 42(f)(1), 42(i)(1)
  • First-year certification to the IRSIRC Section 42(l)(1)
  • Rehabilitation expenditure windowIRC Section 42(e)(3)(A)(ii), (D)
  • Reimbursement / official intent26 CFR Section 1.150-2(d)(1), (d)(2)(i)
  • TEFRA notice and approval validity26 CFR Section 1.147(f)-1(d)(4), (f)(7)
  • Applicable fraction fixed in year one26 CFR Section 1.42-5(b)(1)(viii)
  • Record retention26 CFR Section 1.42-5(b)(2); 4 CCR Section 10337(c)(2)(A)
  • Monitoring frequency and first inspection26 CFR Section 1.42-5(c)(2)(iii)(A); 4 CCR Section 10337(c)(4)
  • Start of construction; 10% test and land ownership4 CCR Sections 10328(c), 10328(d)
  • Reservation Exchange (placed-in-service relief)4 CCR Section 10328(g)
  • Placed-in-service package, permanent conversion, 8609 conditions4 CCR Section 10322(i)(1)(A), (i)(1)(C), (i)(2)
  • Negative points regime4 CCR Section 10325(c)(2), (c)(2)(C), (c)(2)(K), (c)(2)(T)
  • Readiness re-underwriting4 CCR Sections 10325(c)(7), 10328(c)
  • Performance deposit refund and forfeiture4 CCR Section 10335(e)(2)–(e)(3)
  • Compliance monitoring fee4 CCR Section 10335(f)
  • 4% development timetable and placed-in-service package4 CCR Section 10326(j)(3), (k)
  • Nonprofit right of first refusal before 86094 CCR Section 10337(a)(3)
  • 100% affordable recertification exemption and student checks4 CCR Section 10337(b)(1); IRC Section 142(d)(3)(A)
  • NSPIRE adoption4 CCR Section 10337(c)(4)(B)
  • Bond issuance deadline and reversionCDLAC Section 5010(a)(1)–(2), (d)
  • Post-issuance notification and Report of Action TakenCDLAC Section 5012(a), (b)
  • CDLAC performance deposit forfeitureCDLAC Section 5006(c)
  • TIC signature window; InspectCheck transitionCTCAC Compliance Policy Updates memo, July 9, 2026
  • HOTMA implementation datesCTCAC HOTMA Guidance memo, August 4, 2026

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.