Skip to content

Cost certification, the 10% test, and getting to Form 8609 — Utah

Phase 10 of 11

"We just closed and broke ground -- what does UHC actually require while we build, when does the 10% test happen, and what has to happen before UHC will issue our Forms 8609?"

Not yet coveredConstruction runs on the deal's own schedule, but two clocks bound it. Federally, IRC Section 42(h)(1)(E) voids a Housing Credit allocation if the building is not placed in service by the close of the second calendar year after the year of allocation, unless the project has a binding Carryover Allocation Agreement and has incurred more than 10% of its reasonably expected basis within one year of that allocation -- the exception Section 42(h)(1)(F) provides. UHC's own QAP does not restate that federal citation; it simply requires the same Carryover package and 10% test as a matter of its own process. On the back end, UHC adds a Final Cost Certification deadline of 6 months after the last building's Certificate of Occupancy (new construction) or Final Inspection Report (rehabilitation), and commits to issuing Forms 8609 within 90 days of a complete package.

The federal placed-in-service clock, and how UHC's own Carryover mechanics implement it

Under federal law, a Housing Credit allocation is treated as if it had never been made if the building is not placed in service by the close of the calendar year that is two years after the calendar year of allocation (IRC Section 42(h)(1)(E)), unless the project owner has entered into a binding Carryover Allocation Agreement and, within one year of that allocation, has incurred more than 10% of the project's reasonably expected basis (IRC Section 42(h)(1)(F)). Utah's QAP does not restate this statutory citation anywhere in its own text -- its Carryover section simply says the Applicant will be required to enter into a Carryover Allocation Agreement 'if the project is not placed in service by the end of the calendar year in which the Housing Credit Reservation is issued,' and defers to Section 42 generally for 'additional information and certification requirements.' The practical effect is the same: UHC's own Carryover package and 10% Cost Certification are the vehicle through which the federal two-year deadline and 10% test actually get enforced on a Utah deal.

Carryover Allocation deadlines and fees
RequirementDeadlineConsequence of missing it
Carryover Allocation package submitted to UHCNovember 1 of the Reservation yearCarryover Allocation Fee rises from $500 to $1,000 if received after November 1 (but before December 1)
Executed Carryover Allocation Agreement returned to UHCDecember 1 of the Reservation year$500 late fee applies
Extended Carryover fee (each subsequent year Reservation stays active pre-PIS/8609)January 1 of each following year$500 per year
10% Cost Certification30 days after the one-year anniversary of the Carryover Allocation$500 late fee; may jeopardize validity of the Carryover
Attorney-or-CPA written certification that costs were "examined" and it is their "belief" that 10%+ of basis was incurred -- not described in the QAP as an audit10% Cost Certification standard
$50010% Cost Certification late fee
Minimum of 4: Application, Equity investor admission, 10% test/Carryover, Form 8609 submissionUnderwriting checkpoints before 8609

Cost certification: a two-stage process, and an assurance standard the QAP itself leaves unstated

The 10% Cost Certification (Exhibit 5D) requires three things: an Excel cost schedule from the owner, a written certification from a 'qualified attorney or CPA' who has 'examined all eligible costs incurred' and states their 'belief' that the owner has incurred at least 10% of reasonably expected basis, and a separate owner certification under penalty of perjury. Notably, the QAP frames this as an examination and a belief-based opinion -- it does not use the word 'audit' anywhere in Exhibit 5D, and it accepts either an attorney or a CPA for the sign-off.

The Final Cost Certification (Exhibit 5G) is due within 6 months after the last building in the project receives its Certificate of Occupancy (new construction) or its Final Inspection Report from the local governing agency (rehabilitation). The submission package is built from three files UHC provides: a Checklist.xls cover sheet carrying the owner's certifications, a CPA FNL.doc forwarded to the project's CPA for completion and signature, and an FnlCert.xls workbook containing both owner and CPA cost schedules, all printed, signed, and submitted electronically as a bookmarked PDF. Nowhere in this exhibit, or anywhere else in the QAP, does UHC specify whether the CPA's engagement must rise to the level of a full audit, a review, a compilation, or agreed-upon procedures in AICPA terms -- the one place the QAP does use the word 'audit' is a separate provision requiring the project owner's CPA to 'complete an audit and evaluation of all fee and overhead contracts with related or unrelated parties,' which is a narrower review of Developer/contractor fee reasonableness, not a description of the cost-certification schedules themselves. A team assuming a specific assurance level (particularly a full GAAS audit, the standard some other states require outright) should confirm that expectation directly with UHC's Multifamily Finance & Development staff rather than infer it from the QAP text.

Final Cost Certification deadlines and fees
Project typeDeadlineLate fee
New constructionWithin 6 months of the last building's Certificate of Occupancy$1,000
RehabilitationWithin 6 months of the last building's Final Inspection Report$1,000
Same-year Form 8609 issuanceComplete package (all findings resolved) by September 308609s not issued until the following year if missed; Carryover Allocation required for the interim
Substantial post-submission changesN/AAdditional review fee of up to $500

Construction-period inspection: a narrower footprint than a quarterly regime, then one inspection tied to 8609 issuance

The QAP's clearest statement of construction-period inspection authority sits inside 'Additional Requirements for Rehabilitation Projects': 'UHC may inspect all projects upon Application and during construction to verify that work was performed according to what was itemized in the Application or subsequent documents.' That authority is written specifically for rehabilitation deals. Outside that clause, this research found no quarterly or monthly construction-monitoring inspection cadence, no dedicated construction inspector or inspection fee, and no separate safety-versus-quality noncompliance tracking during the build itself anywhere in the QAP or the Compliance Manual -- a materially lighter apparatus than states that assign a contracted inspector to make scheduled visits throughout the build. Confirm this gap directly with UHC if a project's underwriting assumes a specific inspection cadence during construction; the absence of QAP text on the subject is a finding of this research, not proof that UHC never inspects an active job site.

The one inspection the QAP does describe explicitly happens at the back end: 'UHC will issue IRS Forms 8609 reporting the amount of credits allocated to a project following receipt of the complete Final Cost Certification package... and after any outstanding fees are paid to UHC and inspection of completed project is conducted by UHC staff. The inspections are to ensure that representations made in the Application have been fulfilled. This inspection will take place simultaneously with the Final Cost Certification review in order to expedite the Form 8609 processing.' UHC commits to issuing Forms 8609 within 90 days of receiving a complete Final Cost Certification packet, and will reduce the Housing Credit allocation at final Allocation if Application commitments were not honored.

Within 90 days of a complete Final Cost Certification package8609 issuance commitment
Concurrent with Final Cost Certification review, not a separate site visitCompletion inspection timing
UHC will reduce the Housing Credit allocation at final Allocation if Application commitments are not honoredConsequence of unresolved cost overrun

UHC's fee schedule across the construction period

UHC fees, Application through Form 8609
FeeAmountTrigger
Application Fee$2,500 (federal only) / $3,500 (federal + state) / $1,000 (state only) / $2,500 (501(c)(3) bonds); reduced per-unit fees under 10 unitsDue with Application
Reservation FeeGreater of $2,500 or 3% of annual federal Housing Credit amount, plus $1,000 for State CreditsDue within 15 days of Reservation letter (9%); at investor closing (4%)
Carryover Allocation Fee$500 (by Nov. 1) / $1,000 (after Nov. 1, before Dec. 1); $500/year extended carryover fee thereafterWith Carryover package
Allocation FeeGreater of $3,000 or 5% of annual Housing Credit amount (10+ units); $300/unit (under 10 units)Due before release of Forms 8609
Initial Compliance Monitoring Fee$500 + $35/unit (under 26 units) or $1,000 + $35/unit (26+ units), for 2017-and-forward allocationsAssessed at Form 8609 issuance; prorated to the next Feb. 1 cycle
Subsidy Layering Review Fee$500 (Risk Share/LIHTC) or $750 (other)If RD or HUD financial assistance triggers a Section 911 subsidy layering review
Subordination Fee$500 per subordination agreementAny lien/agreement requiring subordination to the LURA
Documentation Revision Fee$500 minimumUnique requests or changes to UHC-required documents (LURA, Form 8609, Carryover Agreements, etc.)
Credit Exchange Fee$2,5009% credit exchanges (encompasses Documentation Revision, additional Carryover, and Mutual Consent for Return fees)

The Initial Compliance Monitoring Fee is named for compliance monitoring but is actually assessed and billed at Form 8609 issuance -- i.e., it is a construction-period-end cost to budget for alongside the Allocation Fee, not a cost that first appears once compliance monitoring begins.

Builder, contractor, and developer cost limits tested across four rounds of underwriting

UHC underwrites a project's financial feasibility a minimum of four times: at Application, prior to admission of the Equity investor/partner, at the 10% test for Carryover Allocation, and again at submission of documents requesting Form 8609. Each pass tests the same cost caps, so a number that cleared Application review can still be flagged at Final Cost Certification if actual costs drifted.

Builder and developer fee limits (2027 QAP)
FeeLimitBasis
Acquisition Fee6%Building(s) acquisition cost (purchase price minus land value and related-party fees/commissions)
General Requirements7%Direct construction (site work + rehab/new construction + contingency, minus General Requirements) in Eligible Basis; additional fee may sit outside basis
Builder Profit and Overhead5%Direct construction in Eligible Basis; additional fee may sit outside basis
Developer Fee (9% projects)15% / 12% / 11% / 10% of Qualified BasisBy unit count: 1-40 / 41-100 / 101-200 / 201+
Developer Fee (4% projects)17% / 14% / 13% / 12% of Qualified BasisSame unit-count bands

Up to 50% of the Developer Fee/Owner Equity may be deferred at Application as a firm financing source. Only a portion of any later credit-pricing increase may be used to pay it down, and reducing the deferred balance beyond what was committed at Application will cause UHC to reduce the credit allocation at Final Cost Certification.

Two notable absences from this cost-limit structure: no construction contingency percentage cap appears anywhere in the QAP's Fee Limits table or Exhibit 4A Underwriting Guidelines (contingency is folded into the 'Direct Construction' base used to calculate the General Requirements and Builder Profit/Overhead caps, but is not itself capped), and neither the QAP nor the Compliance Manual imposes a prevailing-wage or labor-standard requirement on Housing Credit construction. Utah repealed its own state prevailing-wage statute in 1981 and has not re-enacted one, so federal Davis-Bacon wage rules only reach a Utah Housing Credit build if a separate federal funding source -- HOME above the applicable unit threshold, USDA Rural Development financing, or another federally assisted source -- independently triggers them; the Housing Credit allocation itself does not.

Where this goes wrong

  • Assuming Utah runs a quarterly or monthly construction-inspection regime the way some other states' agencies do. The QAP's only stated construction-period inspection authority is written specifically for rehabilitation projects; outside that clause, this research found only a single completion-stage inspection tied to the Final Cost Certification review, with no dedicated construction inspector, inspection fee, or periodic cadence described anywhere.
  • Treating the Final Cost Certification's CPA sign-off as a full audit opinion. UHC's own packet calls for a CPA-completed and -signed cost schedule (CPA FNL.doc / FnlCert.xls), but the QAP text never states whether that engagement must be an audit, a review, a compilation, or agreed-upon procedures -- confirm the expected assurance level directly with UHC before assuming any particular standard.
  • Missing the 10% Cost Certification's actual due date -- 30 days after the one-year anniversary of the Carryover Allocation, not the Application date or the Reservation date -- and its $500 late fee.
  • Assuming a construction contingency percentage cap exists in Utah. No contingency limit was found anywhere in the 2027 QAP's Fee Limits table or Exhibit 4A Underwriting Guidelines; contingency is folded into 'Direct Construction' for computing the 5% Builder Profit/Overhead and 7% General Requirements caps but is not itself capped in the QAP text.
  • Missing the September 30 cutoff for same-year Form 8609 issuance. If a complete Final Cost Certification (with all findings resolved) isn't in hand by that date, Forms 8609 will not be issued that calendar year -- the project must instead execute a Carryover Allocation Agreement, and if that agreement isn't executed by both parties before year-end, the credits are forfeited entirely.
  • Assuming federal Davis-Bacon or a state prevailing-wage law applies to a Utah Housing Credit build. Utah repealed its own prevailing-wage statute in 1981 and has not replaced it, and neither the QAP nor the Compliance Manual imposes a UHC-specific wage standard; Davis-Bacon only attaches if the project separately layers in HOME, USDA RD, or another federal funding source that independently triggers it.
  • Deferring more than 50% of the Developer Fee/Owner Equity at Application and assuming it can be paid down freely later. Only a portion of any later credit-pricing increase may be used to pay down the deferred fee, and reducing the deferred balance beyond what the Application committed to will cause UHC to reduce the credit allocation at Final Cost Certification.
  • Treating the Allocation Fee as a flat number. It is the greater of $3,000 or 5% of the annual Housing Credit amount for projects with 10 or more units (including bond deals), not a fixed fee, with a separate $300-per-unit fee below 10 units.
  • Forgetting to budget the Initial Compliance Monitoring Fee as a construction-period-end cost. Despite its name, it is assessed and billed at Form 8609 issuance -- $500 + $35/unit (under 26 units) or $1,000 + $35/unit (26 or more units) for 2017-and-forward allocations -- not once ongoing compliance monitoring begins.
  • Assuming the underwriting that produced the Application numbers is the last word. UHC re-underwrites the deal a minimum of four times -- Application, Equity admission, the 10% test/Carryover, and Form 8609 submission -- and can reduce the credit allocation at any of the later three if Application commitments aren't honored.

At a glance

Federal placed-in-service deadline
Close of the 2nd calendar year after the year of allocation (IRC Section 42(h)(1)(E)); extendable via a binding Carryover Allocation Agreement conditioned on the 10% test (Section 42(h)(1)(F))
Carryover package due to UHC
November 1 of the Reservation year
Executed Carryover Agreement due back
December 1 of the Reservation year ($500 late fee if missed)
Extended Carryover fee
$500/year, due January 1, for each year the Reservation stays active without placed-in-service/8609
10% Cost Certification due date
30 days after the 1-year anniversary of the Carryover Allocation; $500 late fee
10% Cost Certification standard
Written attorney-or-CPA certification of an "examination" and "belief" that 10%+ of basis was incurred -- not described in the QAP as an audit
Final Cost Certification due date
Within 6 months of the last building's Certificate of Occupancy (new construction) or Final Inspection Report (rehab); $1,000 late fee
Same-year Form 8609 cutoff
Complete Final Cost Certification (findings resolved) by September 30
Form 8609 issuance commitment
Within 90 days of a complete Final Cost Certification package; site inspection conducted simultaneously
Allocation Fee
Greater of $3,000 or 5% of annual Housing Credit amount (10+ units); $300/unit under 10 units
Initial Compliance Monitoring Fee (2017+ allocations)
$500 + $35/unit (under 26 units) or $1,000 + $35/unit (26+ units), assessed at Form 8609 issuance
Builder Profit and Overhead cap
5% of Direct Construction in Eligible Basis
General Requirements cap
7% of Direct Construction in Eligible Basis
Developer Fee cap
15%/12%/11%/10% of Qualified Basis (9% deals) or 17%/14%/13%/12% (4% deals), by unit count; max 50% deferrable at Application
Construction contingency cap
Not specified anywhere in the QAP text (confirmed absence, not an oversight of this research)
Prevailing wage
No Utah state law (repealed 1981, never replaced); no UHC-imposed standard; Davis-Bacon applies only via a separate federal funding source

Governing authority

  • UHC fee schedule -- Application, Reservation, Carryover, Allocation, Initial Compliance Monitoring, Subsidy Layering Review, Subordination, Documentation Revision, and Credit Exchange feesState of Utah 2027 Federal and State Housing Credit Program Allocation Plan (Approved by UHC Trustees 4/23/2026; Approved by Governor Spencer J. Cox 5/12/2026), "UHC FEES"
  • General underwriting requirements; rehabilitation-specific construction inspection authority2027 QAP, "General Project Underwriting and Threshold Requirements" and "Additional Requirements for Rehabilitation Projects"
  • Carryover of Housing Credits; 10% Cost Certification; Final Cost Certification and Form 8609 issuance/inspection2027 QAP, "Carryover of Housing Credits," "10% Cost Certification," and "Final Cost Certification & Issuance of Low-Income Housing Credit Allocation and Certification Forms"
  • Developer, contractor, and general requirement fee limits2027 QAP, "Developer, Contractor and General Requirement Fee Limits," Exhibit 4A Underwriting Guidelines, Exhibit 4E General Requirements Guidelines
  • Carryover Allocation Instructions; 10% Cost Certification instructions; Final Cost Certification instructions and packet contents2027 QAP, Exhibit 5C, Exhibit 5D, Exhibit 5G
  • Statutory placed-in-service deadline and Carryover Allocation/10% test exceptionIRC Section 42(h)(1)(E)-(F) (federal law; not restated by citation in UHC's own QAP text)
  • Utah's repeal of its state prevailing-wage law1981 Utah legislative session (general legislative history; independently verified, not sourced from a UHC document)
  • Initial compliance audit timing (context for the end of the construction phase)UHC Housing Credit Compliance Manual, Multifamily Finance (September 2025), "Initial Audit"

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.