Skip to content

The post-award clock: award to carryover — Texas

Phase 9 of 11

"We won the round. What does TDHCA actually need from us before carryover, and what happens if we miss it?"

Not yet covered3 business days to 11 months from award or reservation

Award day splits into two separate systems

The 9% competitive credit runs on a single annual cycle: one Application Acceptance Period, one Full Application deadline, one Board award meeting in July, with no Round 2 to fall back on. The 4%/bond credit runs all year with no fixed round at all — TDHCA scores and ranks bond pre-applications monthly, and a separate state agency, the Texas Bond Review Board, holds one annual lottery to set queue order for the new year's volume cap. These are two different regulatory architectures sharing one QAP, not one calendar with two credit types.

2026 competitive 9% program calendar
Milestone2026 date
Application Acceptance Period beginsJanuary 6
Full Application Delivery DateFebruary 27
Board issuance of final awardsOn or before July 31
Commitments issuedAugust
Carryover Documentation Delivery DateNovember 2
10% Test Documentation Delivery DateJuly 1, 2027
Placement in Service deadlineDecember 31, 2028
115, requesting $190,306,9872026 9% applications submitted
70, requesting $113,101,835Recommended for award as of July 23, 2026
~61%Hit rate by application count
~59%Hit rate by requested dollars

Treat that hit rate as a single-cycle snapshot computed directly from TDHCA's own dated Application Submission Log and Award and Waiting List Recommendations files, not an audited multi-year rate — and there is no single published statewide 9% credit-ceiling figure to compute a clean oversubscription multiple against the way some other states' annual reports allow.

The single-round design raises the stakes of every date on that table. A deal that is not ready by February 27, or that is not eligible or competitive by the July 31 Board meeting, has no in-year second attempt — the only within-year recourse is the Waiting List, which depends entirely on other applicants' credit being returned.

The Readiness to Proceed election — one point, a deadline the Board will not move

Readiness to Proceed is an elective scoring item worth a single point (unavailable in the At-Risk or USDA set-asides), not a mandatory threshold category. Electing it means certifying that site acquisition and building-permit submission will occur on or before the last day of March of the year following award — March 31, 2027 for a July 2026 award, roughly eight months out.

The QAP states plainly that the Board "cannot and will not waive the deadline" once elected. Waiting List awardees get the March deadline extended by however long they sat on the waiting list before their Commitment issued. Missing it, elected or not chosen carefully, triggers the future-round point penalty described below.

TDHCA's own numbering for this rule is not fully consistent across the document: its Application Submission Log legend cites it as Section 11.9(e)(8), while the QAP's own running text cross-references the same rule once, from within Section 11.9(f)(3) — the future-round-penalty section — as Section 11.9(c)(9). Treat the AppLog citation as the more reliable of the two until the official Texas Administrative Code text resolves which is correct — the same kind of "which artifact actually governs" question worth checking before scheduling anything off a single citation.

Carryover and the 10 percent test

For a 2026 award: Carryover Documentation is due November 2, 2026, and the 10% Test Documentation Delivery Date is fixed at July 1, 2027. That is a single calendar date set by TDHCA's own rule, not simply "12 months from the Carryover Allocation Agreement" — Texas's rule text explicitly incorporates the federal standard (IRC Section 42(h)(1)(E)(i), (ii); 26 CFR Section 1.42-6) rather than restating its own substantive test.

Depending on exactly when the Carryover Allocation Agreement is executed relative to when the federal statute treats the allocation as "made," TDHCA's fixed July 1 date could in some years fall short of the full 12 months the federal statute otherwise allows. This interaction has not been independently resolved here — work to TDHCA's fixed date rather than assuming a full 12 months is guaranteed.

What the 10% Test package must include (10 TAC Section 10.401(a)(1)–(8))
Document
Independent Accountant's Report
Taxpayer's Basis Schedule
Current title and survey
Utility-availability certification
Fair Housing training certificates for controlling principals and the property manager
Guarantor-identification certification from lender and syndicator

A vintage flag worth carrying into any live deal: the Post Award and Asset Management Requirements chapter that contains this rule (10 TAC Chapter 10, Subchapter E) is not necessarily re-adopted every program year the way the QAP itself is — the version behind this guide is filenamed as a 2025 revision. Confirm a 2026-specific update has not superseded a cited fee or day-count before relying on it in a live deal.

Further out, Cost Certification — the point at which the actual HTC amount is fixed, since the Determination Notice figure is only an estimate until then — is due May 15 following the first year of the credit period.

The bond side: no round, a lottery, and a 180-day closing clock

TDHCA accepts multifamily bond pre-applications monthly, scores and ranks each month's batch, and presents winners to its Board the following month for an inducement resolution — which does not itself guarantee final Board approval of the Bond Application.

Separately, the Texas Bond Review Board holds one Private Activity Bond lottery per year to set queue order for the new year's volume cap. For the 2026 program year, the window to file for lottery inclusion ran October 5–20, 2025; the lottery itself was held November 12, 2025 at 1:00 p.m.; and the earliest date reservations begin issuing is January 2. A project needs an adopted Inducement Resolution before it can even enter the lottery.

Priority 1 and 2 lottery applicants get an email when they are next in line, then have exactly 3 business days to have TDHCA staff — not the applicant — confirm the HTC application was submitted; miss it and the Bond Review Board cancels the slot and moves to the next applicant in line, with no further warning. Priority 3 applicants get their reservation first and may file the HTC application whenever they choose. Every application that misses the lottery window is queued strictly by order of receipt afterward and, by statute, ranks below every lottery participant regardless of the Priority tier it would otherwise have carried.

How the residential-rental bond share splits by issuer type
IssuerShare of the residential-rental bond ceiling
Housing finance corporations70%
TDHCA (direct issuer)20%
Texas State Affordable Housing Corporation10%

This sits inside a higher-level split of the entire state ceiling: 32.25% to qualified mortgage bond issuers, 26.25% to qualified residential-rental-project bond issuers, 29.5% to any other issuer.

$1,598,048,078 requested against a $786,601,746 share — roughly 2.0xLocal-HFC share (70%), 2026 requests vs. ceiling
$79,000,000 requested against a $224,743,357 share — undersubscribedTDHCA direct share (20%), 2026 requests vs. ceiling
$16,500,000 requested against a $112,371,679 share — deeply undersubscribedTSAHC share (10%), 2026 requests vs. ceiling

That is a live, weekly-updated 2026 snapshot, not an annual figure. But the pattern is real: the actual competitive bottleneck in Texas's bond program sits specifically inside the local housing-finance-corporation 70% share, not the program as a whole — a developer who assumes "bonds are non-competitive in Texas" because the headline program looks undersubscribed is wrong if filing through the dominant local-HFC channel in a high-demand region.

Once a reservation issues, the closing clock is hard: 180 days for qualified residential-rental-project bonds (150 days for most other issuer categories, 210 days for state-voted, qualified student-loan, and qualified mortgage bond issues).

If the deadline would run past December 31, the issuer may notify the Bond Review Board in writing before December 24 of an election to carry the reservation forward; the Board itself may not file that carryforward election after February 15 of the following year. Within 5 business days of bond closing, the issuer must submit written notice of the delivery date, principal amount, and certified bond documents to the Board.

The closing fee itself is small relative to what is at stake: the greater of $1,000 or 0.025% of the certified bond principal. That is a much lighter financial consequence for walking away than a deposit sized as a percentage of the credit request, and it appears to show up in real behavior — two different cuts of the 2026 Bond Review Board data each show heavy reservation churn, though they do not agree on a single rate: a Dallas/Fort Worth and Houston regional sample found 20 of 33 line items (61%) marked withdrawn, representing $384,000,000 in requested volume against only $300,274,039 that reached closed status across 8 line items; a separate statewide post-regional-collapse tab found a 20% outright-withdrawal rate among 30 applications. Treat both as evidence that reservations are frequently abandoned before closing, not as a single audited annual rate.

There is a real, conditional cap on bond size worth checking before assuming Texas has none: in any year where cumulative reservation requests for qualified residential-rental-project bonds exceed 55.75% of the state ceiling as of October 20, bonds issued for an individual project cannot exceed 55% of its reasonably expected aggregate basis plus land. Below that threshold, there is no percentage cap beyond the federal bond-financing test itself. Whether the 55.75% trigger is currently active is unclear — the Bond Review Board's own program-year page cites an October 20, 2024 figure on a page describing the 2026 program year, which reads as a stale, uncorrected carryover rather than a deliberate lookback; confirm the current-year figure directly before sizing a bond issuance against this cap.

Local building permits follow the same deferred-past-the-gate pattern the 9% side uses for zoning: permits, or evidence they are obtainable subject only to fee payment, are required before bond closing, not before the pre-application, and TDHCA may allow closing to proceed without them case-by-case if lender and investor comfort letters are provided.

Escape hatches: waiting list, force majeure, and short-term delay relief

Three routes back from a missed placed-in-service deadline
MechanismHow it works
Waiting ListApplications not awarded July 31 but still active/eligible go on a waiting list; the Department holds credit returned at Commitment available through September 30 and awards it off the waiting list from confirmed balances; after September 30, awards are made whenever the remaining balance is sufficient, and staff may relax the Carryover deadline for a later waiting-list award
Force Majeure credit returnA Development awarded in any of the preceding three years that returns its credit and cannot finish construction within six months of its original deadline may have the Board — on a detailed factual showing — allocate the returned credit separately from the current year's pool
Unforeseen Short-Term DelayA lighter sibling: if the Development is expected to finish within six months of the original deadline, staff (not necessarily the Board) may approve a same-year re-Carryover with a new deadline no more than six months past the original, on a good-cause standard

Force Majeure is defined with real specificity — acts of God including "significant and unusual rainfall or subfreezing temperatures," loss of utility access from severe weather, explosion, vandalism, military orders, unrelated-party litigation, law changes, national emergency, riot, terrorism, supplier failure, or material/labor shortages — and explicitly excludes anything caused by the Development Owner's own negligence or willful act. The Owner must show construction had already commenced, that reasonable mitigation was taken, that every obligation not impeded by the event was fulfilled, that proper insurance was in place, and that timely notice was given — and must bring the request to the Board within 180 days of the applicable placed-in-service deadline.

Both relief provisions borrow the same federal timing fiction: credit returned after September 30 of the prior program year may be treated as returned on January 1 of the current year.

What failure costs, and who pays it

Texas does not run a single unified negative-points ledger. It uses two narrower, differently shaped mechanisms.

Two ways a miss follows a sponsor
MechanismHow it works
Previous Participation ReviewA threshold eligibility gate, not a point deduction — an Applicant, Developer, or Guarantor found ineligible by the Board under this review is categorically disqualified, full stop
Future-round point penaltyCapped at 2 points per submitted Application, applied for up to two subsequent Application Rounds, triggered by missing a Carryover or 10% Test deadline (or requesting an extension of either), missing federal commitment/expenditure deadlines or Direct Loan contract/closing benchmarks, missing the immediately preceding round's Readiness to Proceed deadline, or an Adherence to Obligations violation

An Adherence to Obligations finding can itself trigger administrative penalties or a point reduction on every application involving that party for the next two rounds — the consequence follows the person and the firm, not just the dead deal, on a narrower and shorter fuse than a points-per-violation regime run indefinitely.

Extension requests for Carryover, the 10% Test, Construction Status Reports, or Cost Certification filed at least 30 calendar days before the original deadline carry no fee; late or last-minute requests cost $2,500, escalating $500 per subsequent extension on the same activity — and a Carryover extension can never be pushed past December 1 of the year the Commitment was issued.

The Compliance Monitoring Fee is smaller than some other states' equivalent, but it is structured differently, not just priced lower: it is an annual recurring fee, not a one-time capitalized cost. For HTC-only developments it is $40 per low-income unit, first invoiced before Form 8609 issuance and collected retroactively from the first year of the credit period, then billed again every year afterward on an anniversary date tied to the month the first building was placed in service. A separate unused-credit penalty of 10% of the unused amount applies if cost certification shows less credit was used than allocated and the excess is not returned, once Form 8609s are issued more than 180 days after the end of the first credit-period year.

Real, named 2026 mid-cycle credit returns
DevelopmentAmount returnedDate
Nova Lofts (fka Cloudhaven)$144,397Jan. 21, 2026
Parkside at Buffalo Bayou$2,000,000Apr. 16, 2026
Eden Heights$12,631Jun. 1, 2026
Woodcrest Apartments$1,627,133Jun. 26, 2026
Westwind of Plainview$1,058,716Jul. 1, 2026

Application-number prefixes show these credits were originally awarded in 2022–2024 rounds and returned mid-cycle in 2026 — real, dated evidence of how long the tail on an already-won award can run before its ultimate fate is known.

Where the window actually breaks

The single-round design turns an ordinary underwriting slip into a full-year loss. Real, named terminations from the 2026 cycle carry explicit "Withdrawn" status in TDHCA's own application log — Legacy Park (Houston), Knoxwood Crossing (College Station), and Desert Springs (Del Rio) among them — though the file that flags the status does not disclose the underlying reason for any one of them.

The notification-not-approval gate at filing does not disappear after award; it resurfaces once construction activity actually starts. Because the threshold requirement is to notify — not to secure sign-off from — the mayor, school district, county, and state legislators, a deal that satisfied the notification rule to the letter can still walk into a hostile council or an unresolved density-based resolution vote once real money is on the table.

Zoning risk resurfaces at exactly the moment this phase is measuring. A site filed under the "pending zoning change" posture has its final approval documentation due at the Commitment or Determination Notice stage, not at Application — so a slow city council can still blow up a deal here, after real money and time have already gone into it, just later in the process than a jurisdiction that required zoning finality before filing at all.

Extension-fee escalation is a slow bleed, not a single failure. Quarterly Construction Status Reports are due the 10th of the month following each calendar quarter (January, April, July, October) until the development is complete, and a late report triggers an automatic fee regardless of whether an extension was requested — a deal team that stops tracking that cadence after initial lease-up can accumulate avoidable fees for the life of the compliance period.

The tail runs past this phase but is set inside it. Placed-in-service closes at the end of the second calendar year following the allocation year — December 31, 2028 for a 2026 award. Extended affordability is elective past that point, not a mandatory state floor: Texas's Extended Use Period is defined exactly at the federal 30-year minimum, with 35, 40, and 45-year commitments available only as scoring points a developer can decline.

Where this goes wrong

  • Assuming a missed February 27 Full Application deadline, or an uncompetitive score by the July 31 Board meeting, has an in-year fallback. It does not — the only within-year recourse is the Waiting List, which depends on other applicants returning credit.
  • Applying the federal 12-month floor to the 10% test instead of TDHCA's own fixed July 1-of-the-following-year deadline. The two can diverge depending on exactly when the allocation is deemed made relative to the Carryover Allocation Agreement's execution date.
  • Treating the elective Readiness to Proceed point as a soft commitment. The QAP states the Board "cannot and will not waive" the March 31 deadline once elected, and missing it feeds directly into the future-round point penalty.
  • Citing the Readiness to Proceed rule by only one subsection number. TDHCA's own AppLog legend and the QAP's running text cross-reference it under two different subsection numbers, and the discrepancy has not been resolved against the official Texas Administrative Code text.
  • Filing a Carryover or 10% Test extension request after the 30-day-ahead window closes. A late request costs $2,500 and escalates $500 per subsequent extension on the same activity, and a Carryover extension can never be pushed past December 1 of the year the Commitment was issued.
  • Booking the Compliance Monitoring Fee as a one-time closing cost. It is $40 per low-income unit billed annually, every year, on an anniversary tied to the placed-in-service month — a model that capitalizes it once will understate operating costs in every year of the hold.
  • Confusing an adopted Inducement Resolution with an entered PAB Lottery slot, or a Priority election with actual queue position after missing the lottery window. A project needs the Inducement Resolution before it can even apply to the lottery, and every post-lottery application ranks below every lottery participant regardless of Priority tier.
  • Missing the 3-business-day window to have TDHCA staff confirm HTC-application submission once the Bond Review Board emails that a Priority 1 or 2 slot is next in line. The reservation is cancelled and moves to the next applicant, with no further warning.
  • Miscalculating the 180-day bond-closing clock against the December 24 / February 15 carryforward window, especially for a reservation issued late in the calendar year.
  • Assuming Texas has no percentage-of-basis cap on bond size at all. A conditional 55%-of-aggregate-basis cap switches on once cumulative statewide residential-rental bond requests exceed 55.75% of the state ceiling as of October 20 — and whether that trigger is currently active was not clearly confirmable from the Bond Review Board's own published page.
  • Treating a bond reservation as committed capital once it issues. Two independent cuts of the same 2026 tracking data each show large reservation-withdrawal shares — a much lower closing fee than a percentage-of-credit deposit appears to make walking away cheap.
  • Filing on a pending zoning change and losing the race between the Commitment/Determination Notice deadline and the local zoning-change hearing calendar — the same underlying local-politics risk the notification rule creates at filing, just resurfacing later and after real money is committed.
  • Letting quarterly Construction Status Report tracking lapse after initial lease-up. A late filing triggers an automatic extension fee whether or not an extension was ever requested.

At a glance

9% single annual round
Full Application Feb 27, 2026; Board award on or before Jul 31, 2026 — no Round 2 fallback
2026 9% hit rate
70 of 115 applications recommended for award (~61% by count, ~59% by dollars) — single-cycle, not audited
Commitments issued
August 2026
Carryover Documentation Delivery Date
November 2, 2026
10% Test Documentation Delivery Date
July 1, 2027 — a fixed calendar date, not simply 12 months from allocation
Placement in Service deadline
December 31, 2028
Readiness to Proceed (elective, 1 point)
Site acquisition + building-permit submission by March 31, 2027; Board "cannot and will not waive"
Future-round point penalty
Capped at 2 points per application, for up to 2 subsequent rounds
Extension fees
Free if filed 30+ days ahead; $2,500 late, +$500 per subsequent extension; Carryover extension can't pass Dec 1 of the Commitment year
Compliance Monitoring Fee
$40/low-income unit, HTC-only — an annual recurring fee indexed to the placed-in-service month, not one-time
Unused-credit penalty
10% of the unused credit amount if 8609s issue more than 180 days after the first credit-period year ends
Bond closing deadline
180 days after reservation (qualified residential-rental-project bonds); 150 or 210 days for other issuer categories
Bond closing fee
Greater of $1,000 or 0.025% of certified bond principal
2026 PAB Lottery
Filing window Oct 5–20, 2025; lottery held Nov 12, 2025; earliest reservations issue Jan 2
Residential-rental bond share by issuer
70% housing finance corporations / 20% TDHCA / 10% TSAHC
Extended Use Period floor
30 years total (federal minimum) — 35/40/45 years available only as elective scoring points

Governing authority

  • 9% program calendar2026 QAP Section 11.2(a)
  • Readiness to Proceed election and non-waivable deadline2026 QAP Section 11.9(e)(8) (the QAP's running text separately cross-references this rule, from within Section 11.9(f)(3), as Section 11.9(c)(9); numbering not fully consistent)
  • Future-round point penalty and Adherence to Obligations2026 QAP Section 11.9(f); Section 11.903; Tex. Gov't Code Section 2306.6710(b)(2), Section 2306.6720
  • Previous Participation Review — categorical eligibility gate2026 QAP Section 11.202(1)(F); 10 TAC Chapter 1, Subchapter C
  • Waiting List mechanics2026 QAP Section 11.6(c)(4)
  • Force Majeure credit-return relief2026 QAP Section 11.6(c)(5)(A)–(H)
  • Unforeseen Short-Term Delay relief2026 QAP Section 11.6(c)(6)(A)–(C)
  • Federal timing fiction for credit returned after September 3026 CFR Section 1.42-14(b)(2)(C)(iii)
  • 10% test and placed-in-service federal standardIRC Section 42(h)(1)(E)(i), (ii); 26 CFR Section 1.42-6
  • Texas 10% test rule, fixed deadline, and required documentation10 TAC Section 10.401(a), (a)(1)–(8)
  • Construction Status Report cadence10 TAC Section 10.401(b)
  • Extension-fee escalation and timing10 TAC Section 10.405(c)
  • Extension-fee schedule and Carryover-extension outer bound2026 QAP Section 11.901(9)
  • Compliance Monitoring Fee2026 QAP Section 11.901(16)
  • Unused-credit penalty2026 QAP Section 11.901(15)
  • Extended Use Period floor and elective scoring2026 QAP Section 11.1, definition (52); Section 11.9, Extended Affordability item
  • Bond pre-application monthly cycle and inducement resolution2026 Multifamily Housing Revenue Bond Rules Section 12.4(a), (d)
  • Local permits deferred to bond closing2026 Multifamily Housing Revenue Bond Rules Section 12.7(a), (f)
  • Volume-cap split among issuer typesTex. Gov't Code Section 1372.022(a); Section 1372.0231(a)
  • Residential-rental reservation priorities and post-Lottery rankTex. Gov't Code Section 1372.0321; Section 1372.0231(j)
  • Bond closing deadline tiers, carryforward window, post-closing noticeTex. Gov't Code Section 1372.042(a), (a-1), (b), (c), (d)
  • Bond closing feeTex. Gov't Code Section 1372.006(b)
  • Conditional aggregate-basis cap on bond sizeTex. Gov't Code Section 1372.037(b)
  • PAB Lottery mechanics (queue priority, 3-business-day confirmation window)Texas Bond Review Board / TDHCA, "Private Activity Bond Reservation & Housing Tax Credit Application Process — FAQ" (last updated 11/13/2024)
  • 2026 bond reservation and closing status dataTexas Bond Review Board 2026 PAB Summary, per Tex. Gov't Code Section 1372.0231 status-reporting requirement
  • 2026 9% application, award, and credit-return dataTDHCA 2026 Competitive HTC Application Submission Log and Award and Waiting List Recommendations (dated June 26 and July 23, 2026)

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.