Skip to content

The post-award clock: reservation to carryover to placed-in-service — Montana

Phase 9 of 11

"MBOH doesn't take a reservation deposit at Award the way I've heard other states do — so what actually proves our 9% award is real, and when does the federal 10 percent test clock actually start?"

Not yet coveredAbout 13 months from Award Determination to a signed Carryover Allocation Agreement — longer than the reservation-to-carryover gap most larger states run — then up to 2 more years to Placed in Service under federal law

Three signatures, three deadlines, before Carryover is real

An Award Determination isn't a Carryover Allocation. After the Board awards Credits, MBOH sends the Owner a Reservation Agreement, and the Owner must return it signed by March 1 of the year following the Award — or by whatever earlier date MBOH specifies as necessary to preserve the Credits (2027 QAP Section X.A). That alone doesn't produce a Carryover Allocation; it only sets up eligibility for one.

Worked example: a Project awarded at the October or November 2026 Board meeting
MilestoneDeadlineWhat's required
Award DeterminationOctober or November 2026 Board meeting—
Signed Reservation Agreement returnedMarch 1, 2027Executed Reservation Agreement (Section X.A)
Carryover package submittedDecember 1, 2027Executed Reservation Agreement + Proof of Ownership + executed/recorded Restrictive Covenants (LURA) + Reservation Fee (Section X.B)
Carryover Allocation Agreement executedBefore December 31, 2027MBOH-issued agreement, signed and returned (Section X.B)
10% Cost Certification (MBOH deadline)≈ December 31, 2028First anniversary of MBOH's execution date (Section X.C)

MBOH's own Fee Schedule calls the December 1 deadline the date the "Reservation fee" is due — but the QAP text makes clear that's shorthand for a four-part package, not a standalone payment: the executed Reservation Agreement, Proof of Ownership, the executed and recorded LURA, and the fee itself all have to arrive together to produce a Carryover Allocation (Section X.B).

No acceptance deposit at Award — but a real penalty for missing the next one

Montana doesn't charge anything at Award itself comparable to a 1-to-4-percent reservation deposit some states collect within weeks of a competitive win. The first money due is the Reservation Fee — 10% of annual credits reserved — and it isn't due until the Carryover package, roughly a year or more after Award (MBOH Housing Credit Fee Schedule). That absence removes an early financial checkpoint that, elsewhere, signals a deal is genuinely moving.

Post-Award fees and late penalties (MBOH Housing Credit Fee Schedule, dated September 1, 2023)
Fee or penaltyAmountTrigger
Reservation fee10% of annual credits reservedWith the Carryover package, on or before Dec. 1
Failure to return Reservation Agreement by deadline25% of the Reservation FeeSubmitted with the late paperwork
10% Test underwriting fee$1,500Submitted with the 10% Cost Certification paperwork
10% Test corrections$100 per corrected, incomplete, or omitted itemSubmitted with the correction
8609 fee$3,000Submitted with the 8609 paperwork
8609 filed past 6 months after last building Placed in Service$5,000Submitted with the paperwork
Re-issuance of 8609 for Developer/Accountant error$1,250Submitted with the paperwork
Completed 8609 not returned to MBOH within 90 days of issuance$1,000Submitted with the paperwork

The posted fee schedule is dated September 1, 2023 — more than two years older than the November 2025-adopted 2027 QAP it prices. Confirm current amounts with MBOH before budgeting.

That 25%-of-Reservation-Fee penalty is the closest thing Montana has to an early skin-in-the-game requirement — it just falls on the back end of the Reservation Agreement step (due March 1 of the year following Award) rather than at Award itself, and it's priced as a percentage of a fee that, at that point, still hasn't been paid.

The 10% test: MBOH's paperwork deadline is longer than the federal floor

MBOH's own text sets the 10% Cost Certification submission deadline at "no later than the first anniversary of the date on which MBOH executed the Carryover Allocation Agreement" (2027 QAP Section X.C) — roughly a full year after Carryover. That is MBOH's paperwork deadline for proving the test to MBOH. It is not the federal deadline for actually incurring the basis, and the two run on different clocks.

Federal law splits the 10% test's incur-by date on when in the calendar year the carryover allocation itself was made: if before July 1, the basis must be incurred by the close of that same calendar year; if after June 30, the taxpayer has only 6 months from the allocation date (26 CFR Section 1.42-6(a)(2)). Because MBOH's Carryover Allocation Agreements are structurally dated in December — the QAP requires execution and return "prior to December 31" of the year the package was filed — a typical Montana deal falls squarely in the after-June-30 bucket. That puts the real federal floor around six months after the December carryover date, roughly six months earlier than MBOH's own first-anniversary paperwork deadline.

First anniversary of the Carryover Allocation Agreement's execution date (≈12 months)MBOH's 10% Cost Certification submission deadline
6 months after the carryover allocation date (26 CFR § 1.42-6(a)(2))Federal 10% test incur-by floor for a post-June-30 carryover
The carryover allocation is invalid and is treated as if it had never been made (IRC § 42(h)(1)(E)/(F))Consequence of missing the federal floor

A developer working only from MBOH's own QAP text could reasonably plan around a full year to reach 10% of reasonably expected basis. Federal law doesn't give that year on a typical Montana timeline — meeting MBOH's submission deadline for the paperwork doesn't retroactively fix a project that didn't actually incur the basis by the earlier federal date. Confirm both dates with MBOH and count from the Carryover Allocation Agreement's actual execution date, not the December 1 package-submission date.

Placed in Service runs on federal time, not an MBOH-specific one

Nothing in the QAP's Section X restates a Montana-specific Placed in Service deadline — it relies on federal law directly. Under IRC Section 42(h)(1)(E) (a building-based carryover allocation) or Section 42(h)(1)(F) (a project-based allocation covering a multi-building Project), every building has to be Placed in Service no later than the close of the second calendar year following the calendar year in which the carryover allocation was made. For the worked example above — a Carryover Allocation Agreement executed in December 2027 — that puts the federal Placed in Service deadline at the close of 2029.

MBOH does re-underwrite the deal along the way rather than treating Carryover as a formality: the same feasibility analysis MBOH runs at Application is repeated "at the time of 10% Cost Certification and at Final Cost Certification prior to issuing IRS Form(s) 8609" (Section III.I) — three separate feasibility checkpoints across the life of the award, not one at Application and then silence until closeout.

The QAP's only stated flexibility on any of these dates is general, not a defined hardship or extension procedure: MBOH may extend or change QAP deadlines by posting a change on its website (Section III.E), and both the Reservation Agreement and Carryover Allocation deadlines are independently qualified with "or by such other date specified by MBOH as necessary to preserve the Credits" (Section X.A–B). There's no published Montana-specific disaster or hardship extension policy comparable to what some larger states publish — a developer needing relief has to ask MBOH directly rather than point to a QAP provision.

Credit Refresh: Montana's own release valve for a stalled award

A Project that's fallen behind schedule isn't limited to losing its Credits outright. Once MBOH has issued a Carryover Allocation and approved the 10% Cost Certification, the Owner can apply for a Credit Refresh — converting the previously awarded Credits from their original Credit year to a more recent one (2027 QAP Section X.E). The request needs a revised Proforma (Excel), a narrative justifying it, and the applicable fee; the Owner or a representative has to appear before the Board to answer questions, and the Board weighs the Development Team's diligence, factors outside its control, and the likelihood the Project gets built either way.

A Credit Refresh can't be used to grow the award — the refreshed amount is capped at whatever was originally allocated or the maximum Credit Award under the Applicable QAP, whichever is lower — and every requirement of the Applicable QAP applies to the refreshed Reservation exactly as if it were the original.

Final Allocation and Form 8609 — and what follows a sponsor afterward

Final Allocation of all Credits requires payment in full of the applicable Fee Schedule amounts, and MBOH may conduct a site visit and file audit before issuing Form(s) 8609 (Section X.F). Two clocks run in opposite directions at the finish line: MBOH assesses a late fee if it hasn't received all required 8609 items within 6 months of the last building's Placed in Service date, and separately requires the Owner to send back a copy of each signed Form 8609 within 3 months of MBOH's issuance — miss either window and the Fee Schedule prices it directly ($5,000 and $1,000, respectively).

The post-award discipline doesn't end at 8609. An Applicant whose first-ever Montana 9% Project is still "In-Process" — no Form(s) 8609 issued, and Credits not returned or rescinded — cannot receive another 9% Award unless it partners with an Experienced Developer entitled under written agreement to at least 50% of the Developer Fee on the new deal (Section II.A). And Appendix D's disqualification provisions reach directly into the post-award record: a debt coverage ratio that "changed significantly" between Application and 10% Cost Certification or Final Allocation, a Development Team member who requested additional Credits more than once, or delinquent late fees owed to MBOH are each independently listed as grounds to disqualify a Development Team member for up to five years — in Montana or, per the same Appendix, on a deal in another state entirely.

Substantial Changes carry their own 30-day advance-notice requirement that spans the whole post-award period through Placed in Service — a list of 20 items in Section X.H, from a Development Team change to a swing in Total Project Cost Per Unit to a shift in income or rent targeting. One item on that list is worth flagging specifically: any change that "would have resulted in a lower Development Evaluation Criteria score" if known at Application is itself a reportable Substantial Change, which means MBOH is asking a sponsor to self-report the kind of drift that would have hurt its own Application.

Where this goes wrong

  • Assuming Montana charges an acceptance deposit at Award. It doesn't — but returning the signed Reservation Agreement late costs 25% of the Reservation Fee itself, even before that fee has been paid (MBOH Fee Schedule; 2027 QAP Section X.A).
  • Reading MBOH's 10% Cost Certification deadline — the first anniversary of the Carryover Allocation Agreement's execution — as the date the 10% basis must actually be incurred by. It's MBOH's paperwork deadline. Because Montana's Carryover Allocation Agreements are routinely dated in December, the federal incur-by floor under 26 CFR § 1.42-6(a)(2) falls roughly six months earlier, around the following June.
  • Treating the Fee Schedule's December 1 "Reservation fee" line as a standalone payment. It's one of four items — executed Reservation Agreement, Proof of Ownership, executed/recorded LURA, and the fee — all due together to receive a Carryover Allocation (2027 QAP Section X.B).
  • Assuming Montana publishes an MBOH-specific Placed in Service deadline. It doesn't — Section X relies on the federal deadline directly: the close of the second calendar year following the year the carryover allocation was made (IRC § 42(h)(1)(E)/(F)).
  • Filing a second 9% Pre-Application before the first Montana 9% Project is fully closed out. An Applicant with an In-Process first Project can't receive another 9% Award unless partnered with an Experienced Developer entitled to at least 50% of the Developer Fee on the new deal (Section II.A).
  • Letting the debt coverage ratio drift between Application and 10% Cost Certification or Final Allocation without flagging it to MBOH. For 2018-and-later Awards, a DCR that "changed significantly" from underwriting is itself a listed disqualification trigger (Appendix D).
  • Missing the 3-month window to return signed Form(s) 8609 to MBOH, or the 6-month-from-last-Placed-in-Service window for the rest of the Final Allocation paperwork. The Fee Schedule prices both directly — $1,000 and $5,000 respectively (Section X.F).
  • Treating any of the 20 Substantial Change categories as something to mention after the fact. MBOH requires 30 days' written notice before implementing the change, not after (Section X.H).
  • Requesting a Credit Refresh before the 10% Cost Certification is approved. MBOH will only convert Credits to a more recent Credit year for a Project that already holds both a Carryover Allocation and an approved 10% Cost Certification (Section X.E).
  • Assuming a poor track record on an out-of-state deal won't reach a Montana post-award file. Appendix D's disqualification standard runs on a Development Team member's record "in Montana or in another state," and can be applied any time MBOH learns of it, not only at Application.

At a glance

Administering agency
Montana Board of Housing (MBOH), Montana Dept. of Commerce
Reservation Agreement return deadline
March 1 of the year following the Award (2027 QAP Section X.A)
Carryover package due
December 1 of the year following the Award — Reservation Agreement, Proof of Ownership, LURA, and Reservation Fee (Section X.B)
Carryover Allocation Agreement execution
Before December 31 of that same year (Section X.B)
Reservation Fee
10% of annual credits reserved (MBOH Fee Schedule)
Late Reservation Agreement penalty
25% of the Reservation Fee (MBOH Fee Schedule)
MBOH's 10% Cost Certification deadline
First anniversary of MBOH's execution of the Carryover Allocation Agreement (Section X.C)
Federal 10% test floor (post-June-30 carryover)
6 months after the carryover allocation date (26 CFR § 1.42-6(a)(2))
10% Test underwriting fee
$1,500, due with the paperwork
Placed in Service deadline (federal)
Close of the 2nd calendar year following the year the carryover allocation was made (IRC § 42(h)(1)(E)/(F))
8609 fee / late fee
$3,000 standard; $5,000 if not submitted within 6 months of the last building's Placed in Service date
Signed 8609 return window
3 months after MBOH issuance ($1,000 late fee)
In-Process Project rule
No 2nd 9% Award until the 1st Montana 9% Project's Form(s) 8609 issue or Credits are returned/rescinded, unless partnered with an Experienced Developer at ≥50% Developer Fee (Section II.A)
Credit Refresh availability
Only after Carryover Allocation issued and 10% Cost Certification approved; amount capped at original Award (Section X.E)
Substantial Change notice
30 days' written notice before implementing any of 20 listed changes (Section X.H)
Extended Use Period
35 years beyond the 15-year Compliance Period — 50-year total

Governing authority

  • Reservation Agreement2027 QAP Section X.A
  • Carryover Allocation package and deadlines2027 QAP Section X.B
  • 10% Cost Certification2027 QAP Section X.C
  • LURA / Declaration of Restrictive Covenants2027 QAP Section X.D
  • Refreshing Credits (Credit Refresh)2027 QAP Section X.E
  • Final Allocations / Form(s) 86092027 QAP Section X.F
  • Changes to Project or Application; Substantial Changes2027 QAP Section X.H
  • Repeat feasibility analysis at 10% Cost Certification and Final Cost Certification2027 QAP Section III.I
  • First Housing Credit Project Must Be Completed (In-Process Project rule)2027 QAP Section II.A
  • Changes and waivers to QAP deadlines2027 QAP Section III.E
  • Definitions: In-Process Project, Experienced Developer, Proof of Ownership, Initial/Carryover Allocation, Final Allocation2027 QAP Appendix A
  • Disqualification — demonstrated management weaknesses (DCR drift, repeat Credit requests, delinquent fees)2027 QAP Appendix D
  • MBOH fee schedule, including post-award fees and late penaltiesMBOH Housing Credit Fee Schedule, dated September 1, 2023
  • Carryover allocation to a qualified building; Placed in Service deadline26 U.S.C. Section 42(h)(1)(E)
  • Project-based carryover allocation; 10% test applied to the entire multi-building Project26 U.S.C. Section 42(h)(1)(F)
  • Carryover-specific 10% test timing (before/after July 1 split)26 CFR Section 1.42-6(a)(2)

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.