"DSHA just sent a Preliminary Reservation letter -- what is the actual sequence of deadlines to a Carryover Allocation, when does the federal 10% test hit, and what happens if a lender falls through before I get there?"
The fork at award: placed in service by November 1, or a Carryover by year-end
The QAP's Placed in Service Requirements state the rule directly: "All developments receiving a Preliminary Reservation of credits must be placed in service either by November 1st of the year in which they receive Reservation or must receive a Carryover Allocation of credit prior to the end of the year in which they have received the Preliminary Reservation." For any development that takes the Carryover path -- which is the realistic path for nearly every new construction or substantial rehabilitation deal -- the next deadline is federal: the development must have "incurred more than 10% of reasonably anticipated development costs, no more than twelve (12) months after the issuance of the Carryover Allocation." DSHA's own text names this requirement "the 10% Test" and requires "written certification from a certified public accountant that they have incurred expenditures for more than 10% of the reasonably-expected basis" by the close of the calendar year of allocation or 12 months from the Carryover date, whichever applies. Developments that miss this procedure are subject to credit allocation revocation, and DSHA's separate Cost Certification and Draw Guide governs the mechanics in more detail. Independent of the 10% Test's own timing, every project -- Carryover or not -- must be placed in service by the end of the second calendar year following the year of allocation, matching the federal two-year outer limit.
The 60-day kickoff meeting and what has to be true before DSHA will execute Carryover
DSHA schedules a kickoff meeting within 60 days of the preliminary award notice, and attendance is mandatory for four specific Development Team roles: the Applicant, the Development Consultant, the Architect, and the General Contractor -- a narrower, named list than "the development team" generally, meaning a missing General Contractor or Architect at this meeting is a real compliance gap, not a formality. Before DSHA will execute the Carryover Agreement itself, the QAP requires: applicable land use approvals or "satisfactory progress" toward them; evidence that the equity investor has been finally selected (not merely a term sheet or short list); the Architect's submission of 80% Plans and Specifications conforming to DSHA's Minimum Design and Construction Standards; a Memorandum of Agreement with the Delaware Transit Corporation; and, where applicable, USDA transfer approval.
The preliminary reservation award itself carries an explicit caveat baked into its own definition: it "is subject to amendment, change, cancelation, or modification based on DSHA's underwriting, satisfaction of conditions to carryover, and the timely finalization of financing commitments." A Preliminary Reservation is a strong signal, not a locked allocation.
The Declaration of Restrictive Covenants, and how broadly DSHA can cancel an allocation
Every award requires "a minimum thirty (30)-year low-income housing commitment," memorialized in a Declaration of Restrictive Covenants that must be "signed, recorded and returned to DSHA before the carryover allocation is awarded or the development is placed in service" -- whichever comes first, on the same logic as the November 1/year-end fork above. DSHA's cancellation authority is written broadly, not narrowly: "Should any of the requirements listed in this document not be met or the characteristics of the development be changed or modified at any time after receiving the Carryover Allocation, DSHA shall have the right to cancel the credit allocation and the owner shall acknowledge the return in full of the credit allocation to DSHA." That is a standing, ongoing condition -- not a single deadline check -- and it runs alongside DSHA's express disclaimer that it "does not represent or warranty that the amount of credit allocated is sufficient to make a development feasible or viable."
The 2026 round's actual dates
| Milestone | 2026 date |
|---|---|
| Applications due to DSHA | April 30, 2026, 3:00 p.m. |
| Preliminary ranking notifications released | On or around July 15, 2026 |
| Carryover submission due to DSHA | November 6, 2026 |
| DSHA executes carryover allocations to selected projects | On or around December 18, 2026 |
The QAP's own 90-day notification commitment (Review and Selection Process) and the 60-day kickoff-meeting requirement both run from the actual notification date, not from these published target dates -- a project should track its own notification letter date rather than assume the published "on or around" date controls its personal clock.
Final closing, cost certification, and an 8609 process that can take 60 days on its own
The final credit allocation happens only once the development is placed in service and DSHA has received cost certification from both the owner/mortgagor and the general contractor, following DSHA's own Cost Certification and Draw Guide and covering all sources and uses of funds including syndication fees. To actually receive IRS Form(s) 8609, DSHA requires the final approved cost certification; proof of the placed-in-service date (a Certificate of Occupancy for each building, or substantial-completion documentation where a local jurisdiction does not issue COs); documentation of all permanent DSHA loan closing requirements, if applicable; registration on Delaware's housing search website; and confirmation that all tenant data has been uploaded to DSHA's database. DSHA states plainly that "the review process may take as long as sixty (60) days to complete," and for any project carrying DSHA financing, "IRS Form(s) 8609 will not be issued until permanent closing" -- meaning a DSHA-financed deal's 8609 timeline is gated by loan closing, not just by the cost-certification review itself.
When a deal cannot hit its date: Forward Reservation, not automatic grace
If circumstances beyond an applicant's control threaten the placed-in-service date, the applicant must notify DSHA "within thirty (30) days of such applicant's knowledge of the delay." The actual request for a return-and-Forward-Reservation of credits, though, is only accepted in a fixed annual window: "between September 16 and November 1 of the applicable year," submitted to DSHA's Director of Housing Development by email or certified mail -- "Requests will not be accepted outside the stated window." The request must name the development and applicant, state the statutory placed-in-service deadline, and document the due diligence performed, the specific cause of delay, and the mitigation steps attempted.
If DSHA agrees the delay is outside the applicant's control, it may allow the credits to be returned without penalty and grant a Forward Reservation of the same dollar amount from a future year -- but only up to two times per development, and each use carries a $15,000 fee that is "non-refundable, non-basis eligible," due before the Forward Reservation is executed. Critically, a project that returns and reapplies "must comply with the current QAP in place at the time of re-application" -- not the QAP its original award was scored under -- and DSHA may require revision of exhibits at its discretion. A Forward Reservation is real re-underwriting risk, not a simple deadline extension: scoring categories, dollar caps, and threshold items can all have changed by the time a returned project comes back.
Appeals, and the fees and cash constraints that follow the award
An applicant who disagrees with DSHA's ranking decision has 15 days from the ranking announcement to submit a written request for reconsideration to the DSHA Director, with "a comprehensive discussion of the basis for the reconsideration" -- the Director's decision "shall constitute final agency action," and if no reconsideration request is filed, the original ranking announcement date itself becomes the date of final agency action.
| Fee | Amount | Due |
|---|---|---|
| Tax Credit LIHTC Allocation Fee | 1.50% of carryover/allocation amount × 10 years | No later than carryover/construction closing |
| Compliance Monitoring Fee | $750/unit ($1,000/unit for Income Averaging) | Before allocation of credits, 8609 issuance, or the Carryover Agreement -- whichever is first, per the QAP text (the Guidelines' own Fee Schedule separately states "due no later than construction closing" for the same fee -- the two documents phrase the trigger slightly differently) |
| Forward Reservation fee | $15,000 per return request | Before execution of the Forward Reservation; non-refundable, non-basis eligible; usable at most twice per development |
These sit on top of, not in place of, the $1,500/$2,000 application-stage fees described in Phase 8.
Cash available to actually repay deferred developer fee or deferred DSHA debt after stabilization is itself capped: DSHA's Underwriting Guidelines limit annual distributions on 9% DSHA-financed deals to 1% of initial equity investment (with accumulated distributions capped at five years' worth), and on 4% DSHA-financed deals to 2% of initial equity investment up to $200,000 annually for up to 10 years -- or until the required cash-flow fee described in Phase 7 is repaid, whichever is shorter -- after which distributions split 50/50 between the development and DSHA until deferred debt is satisfied. Non-DSHA-financed developments are not subject to these caps and follow a standard partnership waterfall instead. A development's Phase 7 deferred-fee plan and its Phase 9 distribution caps are the same math viewed from two different points in the deal's life -- a fee deferral that assumed faster repayment than these caps actually allow will not resolve itself simply by reaching stabilization.
Where this goes wrong
- Assuming the placed-in-service deadline is a rolling "12 months from award" clock. It is a fixed fork tied to the calendar: November 1 of the Reservation year for placed-in-service, or a Carryover Allocation by December 31 of that same year -- not a fixed number of months from the award date.
- Confusing the federal 10% Test's 12-month clock (from Carryover Allocation issuance) with the outer placed-in-service deadline (end of the second calendar year following the year of allocation). Both apply, but they run from different start points and serve different purposes.
- Treating the kickoff meeting's attendance requirement as satisfied by any development team member. The QAP names four specific mandatory attendees -- Applicant, Development Consultant, Architect, and General Contractor -- not the development team broadly.
- Assuming DSHA's cancellation authority is limited to missing a named deadline. The QAP's cancellation language reaches any failure to meet a listed requirement or any change to "the characteristics of the development... at any time after receiving the Carryover Allocation," a standing condition rather than a single trigger event.
- Assuming a Forward Reservation is available whenever a project is genuinely delayed for good reasons. The request window is fixed to September 16–November 1 of the specific applicable year regardless of when the delay is discovered -- outside that window, the mechanism is unavailable no matter how compelling the cause.
- Assuming a returned-and-reapplied Forward Reservation project keeps its original award's scoring, caps, and terms. Reapplication must comply with whatever QAP is in effect at the time of reapplication, which can differ materially from the QAP the original award was scored under.
- Assuming the Compliance Monitoring Fee's due date is identical across DSHA's own documents. The QAP text ties it to whichever comes first among allocation of credits, 8609 issuance, or the Carryover Agreement; the Guidelines' Fee Schedule separately states it is due "no later than construction closing" -- the same fee, described with two different triggers in two DSHA documents that this research could not fully reconcile.
- Assuming DSHA-financed 4% deals can distribute cash flow freely once stabilized. Annual distributions are capped (2% of initial equity up to $200,000/year for up to 10 years, then split 50/50 with DSHA) until deferred DSHA debt is satisfied -- a real constraint on how fast a Phase 7 deferred-fee plan can actually be repaid.
- Missing that 8609 issuance for a DSHA-financed deal is gated by permanent loan closing, not just by DSHA's cost-certification review. The QAP states 8609s "will not be issued until permanent closing" for such projects, independent of the up-to-60-day review timeline.
- Treating the published "on or around" ranking-notification and carryover-execution dates on DSHA's timeline as binding for an individual project. The QAP's own 90-day notification and 60-day kickoff-meeting commitments run from a project's actual notification date, and DSHA reserves the right to amend the published timeline dates outright.
- HUD
- LIHTC
- State QAPs
- IRS § 42
- Housing Finance Agencies
