Skip to content

Site control and due diligence — Delaware

Phase 2 of 11

"We have a purchase contract on the site -- does that satisfy DSHA's site control threshold, and how much environmental and floodplain work does DSHA actually expect before the application is even due?"

Not yet coveredSite control documentation must be in hand and remain valid at application, and must stay valid for at least six months past the application deadline -- DSHA can deem an application ineligible if site control terms are amended after submission. A separate, far more rigorous document package (approved ALTA survey, title binder, final zoning letter, flood plain designation, and wetland delineation) is not due until 30 days before construction closing, which typically falls many months to over a year after a Preliminary Reservation. The Phase I Environmental Site Assessment must be current enough to support the application's own remediation cost estimates, though the QAP does not state a fixed freshness window for it the way it does for the market study.

Site control at application: five acceptable instruments, a six-month validity floor, and a hard rule against amendment

QAP Threshold Requirement 17 accepts five forms of site control: a recorded deed, a recorded long-term lease, a municipal or county disposition and development agreement, an option to purchase or lease, or a purchase contract. Whichever instrument is used, its full terms must be submitted at application and must remain valid for a minimum of six months beyond the tax credit application deadline. DSHA reserves the right to deem an application ineligible outright if the site control documentation is amended after application -- a materially different, and stricter, rule than simply requiring site control to exist at all.

A separate rule applies to any applicant that has secured, applied for, or may apply for federal funding on the development or a later phase: the site control documents themselves must be made contingent on completion of a satisfactory environmental review under federal guidelines. That contingency requirement is a site-control drafting issue, not a later closing condition -- it has to be built into the option, contract, or lease language submitted with the application.

Environmental threshold: the hard knockouts, and the one flood-zone exception that only applies to Preservation deals

QAP Threshold Requirement 26 lists a short set of site conditions that make an application ineligible to compete outright if any building, structure, road, or parking area on the site fails to avoid them: wetlands, a non-remediated Superfund site, land identified as habitat for any federally or state-listed threatened or endangered species, land or soil unsuitable for building and not appropriate for remediation, and land in a 100-year or 500-year flood zone. Compliance has to be verified through the environmental assessment or audit plus a detailed site map -- this is not a self-certification. (The original January 2025 QAP text also listed prime farmland as a sixth disqualifying condition; that item does not appear in the QAP DSHA updated in January 2026 and currently publishes -- see the Site Sourcing and Screening phase for the parallel removal of the QAP's former Investment Level threshold.)

The flood-zone knockout carries one explicit exception: it does not apply to Preservation developments. This creates a real, asymmetric due-diligence posture between the two pools that a screener needs to plan around -- a New Construction or New Housing Creation site cannot be in a 100- or 500-year flood zone at all, while a Preservation (acquisition/rehabilitation) deal can be, but then has to absorb DSHA's flood-resilience design retrofits elsewhere in the Design and Construction/Rehabilitation Standards: raising domestic water heaters and central HVAC equipment above the Design Flood Elevation, and installing backwater valves (ideally alarmed) to prevent storm and sanitary sewer backups during coastal storm surges or heavy precipitation.

Any application including federal financing separately has to demonstrate the ability to comply with federal environmental regulations, including an Environmental Records Review -- language the QAP states without further detail, layered on top of (not a substitute for) the state-level threshold knockouts above.

Two different environmental reports, plus a rehab-only physical-walk checklist -- all required before submission

Every Delaware application -- new construction or rehab -- requires a Phase I Environmental Site Assessment conforming to ASTM E1527-13. Developments with existing structures need a second, separate report on top of that: a Phase I Environmental Audit specifically addressing the structures themselves and their existing materials and conditions, which must include test results for lead in water, lead-based paint, asbestos, radon, and PCBs. Only the executive summary of the Environmental Audit goes in the hard-copy application (the full report goes in the electronic copy), and any remediation cost estimate has to appear both in that executive summary and in the development budget itself -- so the environmental findings and the pro forma have to reconcile, not just exist side by side.

Delaware's environmental due-diligence documents, by when they're required and what they cover
DocumentRequired forWhat it covers
Phase I Environmental Site Assessment (ASTM E1527-13)All developmentsStandard Phase I ESA scope -- site history, current conditions, recognized environmental conditions
Phase I Environmental AuditDevelopments with existing structuresThe structures themselves: lead in water, lead-based paint, asbestos, radon, PCBs
CNA Environmental Due Diligence ChecklistAll rehabilitation projectsA DSHA-specific physical-walk checklist covering 26 named risk categories (USTs, PCB transformers, buried waste, on-lot septic, sinkholes, steep slopes, poor drainage, wetlands areas, mold, radon, and more)
Resilience Evaluation (DSHA Resiliency Assessment Tool)All developments -- threshold item, not scoring-onlySite-specific flooding, excessive-heat, and backup-power risk and mitigation strategy

The CNA Environmental Due Diligence Checklist is separate from, and in addition to, the Phase I ESA/Audit pair -- it is a DSHA-authored physical inspection form (percentage of units inspected, percentage of site walked, observed/possible/not-observed ratings) rather than a third-party environmental report.

The Resilience Evaluation is a threshold requirement under QAP item 21 (DSHA Design and Construction/Rehabilitation Requirements), not a scoring bonus -- every application has to submit one, using DSHA's own Resiliency Assessment Tool, addressing flooding, excessive heat, and backup power specifically. The QAP lists eight named mitigation strategies the evaluation can point to (dry floodproofing, backwater valves, component protection floodproofing, elevated equipment, maintaining backup power to critical systems, an emergency management manual, properly venting or eliminating combustion appliances, and a community resiliency hub), and asks whether outside grants could fund a chosen strategy ahead of DSHA resources for a property the tool flags as higher risk.

The heavier package DSHA actually collects -- 30 days before construction closing, not at application

DSHA's Guidelines to the QAP list the documents required 30 days before construction closing, and it is a materially longer and more rigorous list than anything due at application: an approved ALTA survey signed and sealed by a licensed surveyor, an environmental summary with an approved work plan, a building permit, a DelDOT entrance permit, a DNREC permit and/or Notice of Intent, an approved asbestos abatement project design, a final zoning letter, a flood plain designation, a wetland delineation, a sediment control and storm water management plan approval, fire marshal approval, a copy of the title binder with all listed restrictions and/or easements, and a land survey. An updated ALTA survey is required again at permanent closing.

This means the application-stage site control instrument (deed, lease, option, or contract) and Phase I ESA are only the first, lighter layer of Delaware's actual diligence requirements -- the title binder, ALTA survey, and finalized zoning/flood/wetland determinations do not have to exist until construction closing, which for a Preliminary Reservation made in one round typically falls well into the following year given DSHA's own Carryover deadline (November 6, 2026 in the current cycle) and its target of executing Carryover Allocations by around December 18, 2026. This research did not confirm whether DSHA separately requires an owner's or lender's title insurance policy as distinct from the "title binder" described in the Guidelines -- that distinction should be confirmed directly with DSHA or transaction counsel rather than assumed.

DNREC's own permitting role is referenced by the QAP only as a checklist item (a DNREC Permit and/or Notice of Intent at closing, and DNREC final approvals worth 3 of the 10 Readiness to Proceed points) -- the QAP itself does not describe DNREC's wetlands, subaqueous lands, or coastal-zone permitting process or timeline. A Delaware due-diligence plan involving state (not just federal) wetlands or coastal work should engage DNREC's own Division of Water and Wetlands and Subaqueous Lands Section directly; this research did not independently verify DNREC's specific permit thresholds or processing timelines beyond what the QAP lists as a closing exhibit.

Where this goes wrong

  • Treating the application-stage site control instrument (deed, lease, option, or contract) as the full extent of Delaware's title and survey diligence -- DSHA's actual ALTA survey and title binder requirement does not attach until 30 days before construction closing, which can be a year or more after the application.
  • Amending site control documentation after application submission -- the QAP allows DSHA to deem the application ineligible for exactly this, regardless of whether the amendment was favorable to the deal.
  • Structuring a federally-funded deal's option or purchase contract without a federal-environmental-review contingency clause -- the QAP requires that contingency to be built into the site control documents themselves for any applicant that has secured, applied for, or may apply for federal funding.
  • Assuming the 100-/500-year flood zone knockout applies uniformly to every project type -- it carries an explicit exception for Preservation developments, but that exception does not waive DSHA's separate flood-resilience design retrofits (raised equipment, backwater valves) required elsewhere in the Design and Construction Standards.
  • Submitting only a Phase I Environmental Site Assessment on a deal with existing structures -- DSHA requires a second, separate Phase I Environmental Audit of the structures themselves (lead in water, lead-based paint, asbestos, radon, PCBs), not just the standard ASTM E1527-13 site-history scope.
  • Skipping the CNA Environmental Due Diligence Checklist on a rehabilitation deal on the theory that the Phase I ESA/Audit already covers it -- it is a separate, DSHA-specific physical-walk form required in addition to those reports.
  • Treating the Resilience Evaluation as a scoring-only nicety -- it is a mandatory threshold item (QAP item 21) tied to DSHA's Design and Construction/Rehabilitation Standards, required on every application regardless of flood risk.
  • Assuming a federal environmental review (NEPA/URA) on a federally-financed deal substitutes for Delaware's own state-level permitting -- the QAP lists a DNREC Permit/Notice of Intent and a storm water management plan approval as independent closing requirements on top of any federal review.
  • Assuming DSHA's "title binder" requirement at closing is the same thing as an owner's title insurance policy -- this research found only a title-binder-and-restrictions requirement in the Guidelines and could not confirm whether a separate title insurance policy is independently required; confirm directly with DSHA or counsel.
  • Underwriting the utility benchmarking commitment as a one-time diligence cost rather than a 15-year standing compliance obligation with a strict data-currency requirement (no more than 12 months old).

At a glance

Site control instruments accepted
Recorded deed, recorded long-term lease, municipal/county disposition and development agreement, option to purchase or lease, or purchase contract
Site control validity floor
Must remain valid at least 6 months past the application deadline; amendment after submission risks disqualification
Federal-funding contingency
Site control documents must be made contingent on a satisfactory federal environmental review for any applicant that has secured, applied for, or may apply for federal funding
Environmental threshold knockouts
Wetlands, non-remediated Superfund sites, federal/state threatened-or-endangered species habitat, unremediable soil, and 100-/500-year flood zones (Preservation exception only) -- prime farmland was a sixth knockout in the original Jan. 2025 QAP but was removed in the Jan. 2026 update
Phase I ESA standard
ASTM E1527-13, required for all developments
Phase I Environmental Audit
Required in addition to the Phase I ESA for developments with existing structures; must test for lead in water, lead-based paint, asbestos, radon, and PCBs
CNA Environmental Due Diligence Checklist
Required for all rehabilitation projects; a DSHA physical-walk form covering 26 named environmental risk categories
Resilience Evaluation
Mandatory threshold item (QAP #21) via DSHA's Resiliency Assessment Tool, addressing flooding, excessive heat, and backup power
Closing-stage package (30 days pre-construction-closing)
Approved ALTA survey, title binder with restrictions/easements, final zoning letter, flood plain designation, wetland delineation, DNREC permit/NOI, storm water management plan approval, fire marshal approval, land survey
Utility benchmarking commitment
Minimum 15 years, all owner-paid and a sample of tenant-paid accounts, data no more than 12 months old

Governing authority

  • Site control threshold requirement2025-2026 DSHA LIHTC QAP (as updated Jan. 2026), Threshold Requirements, item 17 (Site Control)
  • Site control exhibit and Realty Transfer Tax note2025-2026 LIHTC Application Detailed Checklist, Exhibit 16 (Site Control)
  • Environmental threshold knockouts and flood-zone Preservation exception2025-2026 DSHA LIHTC QAP (as updated Jan. 2026), Threshold Requirements, item 26 (Environmental Threshold); prime-farmland removal confirmed by comparison with the originally adopted Jan. 2025 QAP, former item 27
  • Phase I ESA and Phase I Environmental Audit requirements2025-2026 LIHTC Application Detailed Checklist, Exhibit 19 (Phase I Environmental Audit and Phase I Environmental Site Assessment)
  • Flood plain/wetlands verification exhibit2025-2026 LIHTC Application Detailed Checklist, Exhibits 17-18 (Detailed Preliminary Plot Plan; Verification of Flood Plain and Wetlands Status)
  • CNA Environmental Due Diligence Checklist2025-2026 DSHA Guidelines to the QAP, DSHA CNA Environmental Due Diligence Checklist
  • Resilience Evaluation requirement and mitigation strategy list2025-2026 DSHA LIHTC QAP (as updated Jan. 2026), Threshold Requirements, item 21 (DSHA Design and Construction/Rehabilitation Requirements)
  • Flood-resilience design retrofits (raised equipment, backwater valves)2025-2026 DSHA Guidelines to the QAP, Design and Construction/Rehabilitation Standards, Plumbing and HVAC sections
  • Construction closing document list (ALTA survey, title binder, zoning letter, flood/wetland determinations, DNREC permit)2025-2026 DSHA Guidelines to the QAP, Construction Closing Requirements
  • Updated ALTA survey at permanent closing2025-2026 DSHA Guidelines to the QAP, Permanent Closing Requirements
  • AE&S application-stage threshold requirements (plot plan, wetland/floodplain, Phase I documentation)2025-2026 DSHA Guidelines to the QAP, Architectural Plans, Engineering and Specification (AE&S) Process, Sec. A
  • Utility benchmarking requirement2025-2026 DSHA LIHTC QAP (as updated Jan. 2026), Threshold Requirements, item 27 (Utility Benchmarking)
  • DNREC final approval as a Readiness to Proceed scoring item2025-2026 DSHA LIHTC QAP (as updated Jan. 2026), Scoring and Ranking, Development Team, Readiness to Proceed
  • Carryover submission and allocation execution dates (2026 cycle)DSHA, 2026 LIHTC Timeline (2026 Annual Funding Round)

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.