Skip to content

Site control and due diligence — Pennsylvania

Phase 2 of 11

"PHFA's Tab 6 says my option can't expire before December 31 -- but December 31 of which year, does my 45-year ground lease actually qualify, and why does Tab 34 tell my preservation deal to ignore the Phase I testing rules I just read in Tab 17?"

Not yet coveredEvery diligence item runs its own separate clock rather than one master clock. A Phase I Environmental Site Assessment is valid for 12 months (24 months with a qualifying update); the Market Study/Housing Needs Assessment for 12 months; an As-Is Appraisal for 12 months; a Project Capital Needs Assessment and its companion Energy Audit (preservation deals only) for 12 months each; utility/water/sewer availability letters for only 60 days; and site control itself is not a rolling number of months at all for a competitive 9% deal -- it has to run through a fixed calendar date tied to that program year's own reservation calendar (December 31, 2025, for the 2025 round), while a 4% Tax-Exempt Bond deal instead needs a control instrument that will not expire for at least nine months after the full Application is submitted.

Site control lives in Tab 6 of the Application, not the QAP -- and it's a date, not a term

PHFA's Tab 6 (Evidence of Site Control) opens with a naming requirement that is easy to miss: "SITE CONTROL MUST BE IN THE NAME OF THE 'APPLICANT' or 'CO-APPLICANT' LISTED IN THE CORE APPLICATION." From there, the freshness rule for a competitive 9% deal is stated as an absolute calendar date rather than a term of months: "For 9% applications, without exception, the site control must be provided through December 31, 2025. An option to purchase a site included in the development may not expire before December 31, 2025." That date is specific to the 2025 round -- the QAP and Application package do not restate a generic rule like "through the end of the current program year" that a developer could apply mechanically to a future cycle; the actual date has to be reconfirmed from whatever year's Tab 6 governs the round being filed.

The obligation does not end at the fixed date if the deal is not yet closed. Tab 6 requires two separate proof-of-payment showings on two separate timelines: "If extension fees or option payments are required to be paid, evidence that the extensions have been paid in full must be provided through the applicable date noted above. If the development receives a reservation of Tax Credits, evidence that the extensions or options have been paid in full through December 31, 2026 will be required within two weeks of the reservation." A 4% Tax-Exempt Bond Application runs on a materially different, application-relative clock instead: "For 4% applications, without exception, the site control must not expire for at least nine (9) months after the full application is submitted."

Acceptable site control instruments and their specific requirements -- Application Tab 6
Instrument or fact patternRequirement
DeedA copy of the deed must be submitted for all parcels included in the Application
Lease agreementCopy of the lease, or an executed agreement to enter into one between all parties; minimum term of 45 years
Option, agreement of sale, or lease from a private partyEvidence of the seller/grantor/lessor's own site ownership (deed or other formal instrument) may be required to verify authority to convey
Property owned by a municipality, redevelopment authority, or other public bodyA letter from its solicitor designating the applicant as the selected developer and stating the sale terms; the Agency may also require deeds or other documentation of the public body's own ownership
Multiple sellersAll agreements must be controlled by one entity, and the buyer named in each agreement must be the same entity
Phased developmentThe site control document must address the specific phase described in the Application; a site control document for the entire parent parcel is not acceptable, and the Agency will not process an Application it cannot use to clearly identify the current phase's site
Quiet titleApplicants must separately list any property in the development subject to the quiet title process

Tab 6 also states that the Agency "will not recognize, at a later date, a value for site acquisition if it was not specifically shown in the initial Application" -- an acquisition-cost figure omitted at filing cannot be added back in after the fact.

Market Study/Housing Needs Assessment: PHFA's own four-part instrument, not a generic third-party study

PHFA requires "a comprehensive Market Study/Housing Needs Assessment ('MS/HNA'), completed within 12 months of the Application date of the housing needs of low-income individuals in the area to be served by the development," and the instrument itself is PHFA's own four-part form rather than an open-format third-party report: "the Market Study/Housing Needs Assessment Form; ... the PHFA Housing Inventory Request Form; ... the Housing Providers Needs Assessment Form; and ... the Comparable Housing Survey Form." The QAP requires the study be "performed and completed by an independent, experienced market analyst specifically qualified in affordable rental markets of Pennsylvania," and warns plainly that "If the MS/HNA is not completed by the appropriate party or is not in the Agency's format, the Application may be rejected and returned to the applicant."

One narrow exception exists: an applicant seeking only PennHOMES funds -- where the development either serves special-needs residents in 100 percent of the units, or is a stable-occupancy preservation proposal not converting to market rate, with a waiting list of at least 10 percent of the units -- has the option to complete the assessment using an independent market analyst or its own resources and data instead of PHFA's standard form.

The consistency requirement is a hard rejection trigger, not a scoring adjustment: "The assumptions used in the MS/HNA (e.g. number of units, housing type, unit mix, projected rents, income targeting) must precisely reflect the information contained in the development's Application. Proposals that include a MS/HNA that is inconsistent with or does not accurately reflect the information submitted in the Application will be rejected." PHFA also reserves the right to order its own competing study at any time and can reject an Application "if Agency staff determines that there will be an adverse impact on the marketability of existing affordable housing developments or initiatives in the area" -- and the completed MS/HNA "shall become the property of the Agency and may be subject to public dissemination."

MS/HNA content requirements that carry their own independent lead times
RequirementDetail
Housing Providers Needs Assessment noticeMust be sent to the Executive Director of the appropriate county/local Housing Authority or Public Housing Agency at least 30 days before the Application deadline, with the response incorporated into the study (or documented non-response)
Capture rate calculationTotal proposed units divided by the number of age- and income-qualified households in the primary market area; the qualifying income test caps total housing expense at 40% of income for general occupancy and 45% for elderly occupancy
Comparable rental surveyA minimum of three unassisted market-rate comparables, each with a color photograph, plus a map identifying the subject and comparables
Site documentationPhotographs of the site from at least two perspectives, dated, plus a street map showing the site, surrounding amenities, and the primary market area boundary

The 30-day Housing Authority notice runs on the third party's own response clock, not PHFA's -- it cannot be compressed by starting the market study late.

Appraisals: as-is is the default trigger list, and it is broader than "acquisition credits only"

PHFA's Tab 7 requires an As-Is Appraisal in a specific, enumerated set of circumstances rather than simply whenever Acquisition Tax Credits are requested. "All properties must be appraised separately unless already deeded as one property, owned by one ownership interest, on one sales agreement," and the appraisal is required wherever any one of several conditions applies: an identity of interest between seller and purchaser; a transfer of title within one year prior to closing (in which case "the recognized value of land will be the lower of the purchase price or the as-is appraised value" and PHFA will "under no circumstances" recognize more than the appraised value); the site being a subdivided parcel from a larger property (requiring values for both the whole property and each subdivided parcel); any request for Acquisition Tax Credits (requiring separate building and land values); any request for points tied to a land or building donation under the Ability to Proceed selection criteria; or, as a residual catch-all, any acquisition cost PHFA does not consider reasonable.

Dated within 12 months of the Application dateAs-Is Appraisal freshness
Uniform Standards of Professional Appraisal Practice (USPAP), subject to PHFA's approvalStandard
Required, dated within days of closing, for any development receiving an Agency Primary MortgageAs-Built Appraisal

New construction and rehabilitation each get their own methodology instructions in Tab 7. Both require a personal inspection, an as-is market value opinion under the same USPAP "most probable price" definition, an estimate of the value contribution (not the cost) of any necessary off-site improvements, and photographs of the subject and all comparables. Rehabilitation appraisals additionally require a separate building-and-land value breakdown and "a total 'As-Is' property value" combining them; both methodologies instruct the appraiser to disregard PHFA financing and Tax Credit availability entirely when estimating value, and to estimate post-completion real estate taxes including any applicable abatement program. A long-term ground lease with an up-front lease value included in development costs needs its own independent appraisal of the leasehold estate specifically -- a separate valuation exercise from the fee-simple as-is appraisal.

Environmental due diligence: a universal Phase I threshold -- with preservation deals routed to a different tab entirely

Section 3.3.5 of the QAP sets a threshold that applies to every Application regardless of construction type: "A Phase I Environmental Site Assessment prepared in accordance with ASTM E 1527-21 and the Agency requirements found in the Submission Guide for Architects... is required for all developments. The report cannot be more than 12 months old at the time the Application is submitted. An updated report provided by the original report's environmental consultant may be provided when the original report is between 12 and 24 months old." Tab 17's own instructions add the specific mechanism for that update: the consultant must certify that the five continued-viability actions listed under Section 4.6, items (i)-(v), of the ASTM E 1527-21 standard have been met. Only the executive summary is submitted with the Application, accompanied by the applicant's certification that any identified issues have been reviewed and budgeted for in the development budget -- unless the summary shows no environmental issues at all, in which case no certification is required.

Required hazard testing for existing buildings -- Application Tab 17 (rehabilitation and demolition)
TestScope and protocol
Lead in waterAt least one test per building (two for buildings over 10,000 sq ft), each consisting of an initial-draw sample and a post-flush sample, taken as far as possible from the water service entrance; not required if all interior and exterior water lines are being replaced
Lead-based paintAny building built before 1978: X-ray fluorescence (XRF) spectrum analysis under HUD's Final Rule, 24 CFR Part 35 (as amended June 21, 2004)
AsbestosAny building built before 1978: survey for suspect asbestos-containing materials, tested by polarized light microscopy (PLM)
RadonLowest floor level of each building, at one test per 2,000 sq ft of basement/ground-floor area, plus a test in each stair tower and elevator shaft remaining in use

For a building scheduled for demolition rather than rehabilitation, only the asbestos test is required. All sampling must be performed by certified personnel and tested by an accredited laboratory, with any result above the applicable "action level" clearly flagged.

Tab 17 then makes a redirect explicit that is easy to overlook: "Preservation development applicants should also refer to Tab 34 'Project Capital Needs Assessment' for testing requirements. Preservation developments are required to follow the Tab 34 testing requirements and not the Tab 17 requirements." The two protocols are not identical -- Tab 34's own radon rule, for example, specifies testing in "at least 100% ground contact units and community spaces plus at least 10% of all units above that with a minimum of one test per floor," a different scope than Tab 17's per-2,000-square-foot rule. Applying the wrong tab's protocol to a preservation deal produces testing that does not satisfy either instruction set as written.

Capital Needs Assessment and Energy Audit: mandatory for every currently-occupied property, not just Preservation Preference competitors

Tab 34 defines its own scope broadly: "For purposes of this Tab, a preservation development is any currently-occupied residential housing development and is not limited to applicants seeking Tax Credits through the Preservation Preference outlined in the Allocation Plan." Any acquisition/rehabilitation deal on an occupied property has to submit both a Project Capital Needs Assessment (PCNA) and an Energy Audit, whether or not it is actually competing for the Preservation Preference described in Phase 1 of this guide.

PCNA five required components -- Tab 34
ComponentWhat it covers
Critical Repair ItemsHealth/safety deficiencies, Section 8 Housing Quality Standards violations, and federal lead-based-paint requirements needing immediate remediation
Twelve-Month Physical NeedsRepairs and deferred maintenance to be addressed within 12 months, restoring the property to its originally-approved rental standard
Long-Term Physical NeedsRepair and replacement items over the following 20 years, including major structural systems
Analysis of Reserve for ReplacementInitial and monthly reserve deposit needed to fund 20-year physical needs, accounting for inflation and the property's Expected Useful Life schedule
CostingA cost estimate covering the Critical Repair Items, the Twelve-Month Physical Needs, environmental hazard abatement, and any Long-Term items scheduled for replacement within the first five years

A minimum of $20,000 per unit in construction costs on major systems and components is required for a development to be considered for funding specifically from the Preservation Preference -- a separate funding-eligibility threshold layered on top of the PCNA's own content requirements.

Both must be dated less than 12 months before the Application submission datePCNA and Energy Audit freshness
An independent third party not involved in designing or preparing drawings/specifications for the developmentPCNA preparer
At least 20% of units, but never fewer than five, covering every unit size and configurationUnit inspection minimum
A Building Performance Institute (BPI) Certified Multifamily Building Analyst; the auditor's current BPI certification must be included in the reportEnergy Audit preparer

The Energy Audit itself is a substantive technical exercise, not a checklist: it requires at least one year of utility billing history (audited financial statements are explicitly not acceptable as a substitute), a site visit sampling at least 10 percent of units across all unit types, ASHRAE Fundamentals Chapter 31 energy modeling calibrated against the prior 12 months of actual usage using DOE-approved software such as TREAT or EA-QUIP, and an economic analysis using a Savings-to-Investment Ratio (SIR) -- "the present value of the lifetime dollar savings divided by the cost of the installed measure (a discount rate of 3% must be used)" -- to prioritize recommended measures, based on total installed cost rather than incremental cost.

Utility allowances: six IRS-recognized paths, and PHFA has taken itself off the list

Utility allowance determination in Pennsylvania runs on the same federal framework as every state -- Treasury Regulation 1.42-10 -- and Tab 19 walks through the same building-type hierarchy: RHS-assisted buildings use the RHS allowance; HUD project-based-assistance buildings use the applicable HUD allowance; HOME-assisted units require an individual allowance calculated either through the HUD Utility Schedule Model or a project-specific determination (with PHFA acting as the HOME Participating Jurisdiction for PennHOMES purposes, though "the Agency is considered the Participating Jurisdiction, but will not be the calculator of the utility allowance"); and buildings receiving tenant-based HUD assistance use the local Public Housing Authority's Section 8 utility allowance.

For every other Tax Credit building, Tab 19 lists the same menu of methods the IRS regulation recognizes -- the local PHA utility allowance, a written estimate from the local utility company, an estimate from "the Agency having jurisdiction over the building" (i.e., a state-issued utility allowance), the HUD Utility Schedule Model, or an energy-consumption model prepared by a Pennsylvania-licensed professional engineer -- and then closes off one of those options directly: "An estimate from the Agency having jurisdiction over the building, provided the Agency agrees to provide it. In Pennsylvania, this Agency is PHFA, which has determined that it will not issue utility allowances on new Applications." A developer counting on a PHFA-issued utility allowance the way some other states' housing finance agencies provide one will not get it -- the choice is effectively narrowed to the remaining four IRS-recognized methods.

Utility documentation and timing requirements -- Tab 19
RequirementDetail
Same method for every unit"The same method must be used for calculating all applicable utility allowances" across the development
Availability lettersSewer/water authorities and electric/gas companies must confirm the development can be accommodated within current system capacity, including monthly/quarterly rates and billing structure; dated within 60 days of the Application deadline -- "the Agency will not accept a previous year's submission"
Preservation substituteCurrent utility bills verifying the account is not delinquent may be submitted in lieu of availability letters
HOME-assisted deals specificallyWater and sewer utilities must be project-paid, not billed to tenants, and all units designated for conversion to homeownership must be individually metered
Ongoing obligationAll owners must participate in PHFA's Energy Benchmarking program, assessing and reporting energy performance at least annually using Energy Star Portfolio Manager or a similar tool

The water/sewer project-paid rule and the homeownership-conversion metering rule appear in Tab 19 specifically in the HOME-funds discussion; confirm with PHFA whether either rule extends to a Tax-Credit-only deal with no HOME funds in the capital stack before assuming it does.

Where this goes wrong

  • Treating "site control must run through December 31" as a generic year-end rule that repeats identically every cycle. It is a fixed date tied to that specific program year's own Tab 6 (December 31, 2025, for the 2025 round) -- reconfirm the actual date for whatever round is currently open.
  • Tracking only one paid-through obligation on an option or lease extension. Tab 6 requires proof of payment through the Application-year date at filing, and a second proof of payment through the following year's December 31 within two weeks of receiving a reservation -- missing the second deadline is a distinct failure from missing the first.
  • Assuming a shorter ground lease term satisfies PHFA's site control instrument. Tab 6 sets a 45-year minimum lease term -- a term drawn from another state's LIHTC practice may fall short.
  • Submitting a site control document that covers the entire parent parcel for a phased development instead of the specific phase in the Application. Tab 6 states plainly that a site control document for the whole parcel "is not acceptable" when only one phase is being filed.
  • Retaining a market analyst without confirming Pennsylvania-specific affordable-market experience, or letting the study's assumptions drift from the Application's own unit count, rents, or income targeting. PHFA requires an analyst "specifically qualified in affordable rental markets of Pennsylvania," and any inconsistency between the MS/HNA and the Application is a stated rejection ground, not a scoring deduction.
  • Forgetting to send the Housing Providers Needs Assessment to the local Housing Authority at least 30 days before the Application deadline. That lead time runs on the Housing Authority's own response clock and cannot be compressed by starting the market study late.
  • Assuming an appraisal is only required when Acquisition Tax Credits are requested. PHFA's trigger list is broader -- an identity of interest, a title transfer inside the prior 12 months, a subdivided-parcel valuation, land/building donation points, or simply an acquisition price PHFA does not find reasonable can each independently require an As-Is Appraisal.
  • Applying Tab 17's general Phase I testing protocol to a preservation deal. PHFA's own instructions redirect preservation applicants to Tab 34's testing requirements instead, and the two protocols differ in scope -- for example, Tab 34's radon-testing rule is not the same as Tab 17's.
  • Assuming the Project Capital Needs Assessment is required only for developments actively competing for the Preservation Preference. Tab 34 defines "preservation development" as any currently-occupied residential housing development, which sweeps in acquisition/rehab deals scoring under an entirely different Preference or none at all.
  • Expecting PHFA to issue its own utility allowance estimate. PHFA has affirmatively stated it will not issue utility allowances on new Applications, closing off that IRS-recognized method entirely in Pennsylvania.
  • Letting a utility availability letter go stale. PHFA requires it dated within 60 days of the Application deadline and will not accept a prior year's letter even if it is technically less than 12 months old.
  • Assuming the HOME-program water/sewer project-paid rule and homeownership-conversion metering rule in Tab 19 apply to every Tax Credit deal. As written, those specific rules appear in the tab's HOME-funds discussion -- confirm their reach with PHFA before assuming they bind a deal with no HOME funds involved.

At a glance

Site control naming
Must be in the name of the Applicant or Co-Applicant listed in the Core Application
9% site control freshness
Must run through a fixed date tied to the program year (December 31, 2025, for the 2025 round) -- not a rolling term
4% site control freshness
Must not expire for at least 9 months after the full Application is submitted
Minimum lease term
45 years
MS/HNA freshness and format
Within 12 months of the Application date; PHFA's own four-part form; PHA notice due at least 30 days pre-deadline
As-Is Appraisal
Within 12 months of the Application date; USPAP standard; six enumerated trigger conditions
Phase I ESA
ASTM E 1527-21; within 12 months (24 months with a certified update); executive summary plus applicant certification submitted
Preservation environmental testing
Follows Tab 34's protocol, not Tab 17's -- an explicit PHFA redirect
PCNA / Energy Audit freshness
Both within 12 months of the Application date; PCNA independent third-party prep; Energy Audit by a BPI-Certified Multifamily Building Analyst
PCNA funding threshold
$20,000/unit minimum in major-systems construction cost to be considered for Preservation Preference funding
Utility allowance
PHFA "will not issue utility allowances on new Applications" -- one of six IRS-recognized methods is unavailable in Pennsylvania
Utility availability letters
Dated within 60 days of the Application deadline; no prior-year submissions accepted

Governing authority

  • Evidence of Site Control -- instruments, naming, freshness dates, phased-development rulePHFA 2025/2026 Multifamily Housing Application, Tab 6 (Evidence of Site Control)
  • Market Study/Housing Needs Assessment requirements and rejection grounds2025/2026 QAP, Section 3 (referencing MS/HNA); PHFA Application, Tab 4 (Market Study/Housing Needs Assessment)
  • As-Is and As-Built Appraisal trigger conditions and methodologyPHFA Application, Tab 7 (Appraisals)
  • Phase I Environmental Site Assessment threshold requirement2025/2026 QAP, Section 3.3.5 (Environmental Site Assessment)
  • Phase I testing protocols and preservation-deal redirect to Tab 34PHFA Application, Tab 17 (Phase I Environmental Review/Environmental Test Results)
  • Project Capital Needs Assessment and Energy Audit requirementsPHFA Application, Tab 34 (Project Capital Needs Assessment & Energy Audit)
  • Utility allowance methodology, PHFA's non-issuance policy, and availability-letter requirementsPHFA Application, Tab 19 (Utility Information); 26 CFR § 1.42-10
  • HUD Final Rule on lead-based paint testing24 CFR Part 35, as amended June 21, 2004
  • ASTM Phase I Environmental Site Assessment standardASTM E 1527-21
  • Uniform Standards of Professional Appraisal PracticeUSPAP (Appraisal Standards Board)

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.