Skip to content

Site control, title, and the diligence clocks — New Hampshire

Phase 2 of 11

"NH Housing only asks for 'secure site control' at application — so what actually has to be locked down, and when do title, survey, and the Phase I actually come due?"

Not yet coveredRoughly 9–10 months minimum, start to Progress Phase, in a single uneventful 9% cycle: site control has to be in hand before the July preliminary-application deadline and held continuously through a Progress Phase submission due within 120 days of the December reservation vote — with Carryover (October 1 of the credit year) and Final Allocation each independently re-checking it after that. No aggregate figure is published anywhere in the QAP; this is arithmetic from one round's own posted dates, not a state-set duration.

One agency, and a site-control threshold that asks for almost nothing

The same structural inversion that drives LIHTC everywhere applies here: the tax credit equity that pays for the land doesn't exist until an award does, so a developer almost never closes on a New Hampshire site before winning a reservation. But New Hampshire doesn't split that problem across three regulators the way California does (CTCAC, CDLAC, HCD) or run two parallel clocks the way Texas does (TDHCA plus the Bond Review Board). New Hampshire Housing Finance Authority — "NH Housing," created under RSA Chapter 204-C — is the state's sole LIHTC allocating agency for both 9% and 4% credits.

Its site-control threshold is two sentences. HFA 109.06.F reads in full: "Applicant must have secure site control. Site control may be in the form of an executed Option to Purchase, Agreement to Enter into a Lease, or other legal form of site control." There is no minimum term specified anywhere in the QAP's own text, no extension-ladder requirement, and no execution-date freshness window — nothing resembling CTCAC's evidence-of-executed-extensions rule or Texas's itemized 45-year-minimum-lease list.

That brevity is easy to misread as "site control barely matters here." It doesn't mean that — it means NH Housing defers the actual verification of site control downstream, checking it independently at three later checkpoints instead of loading requirements onto the application. The next section is where those checkpoints actually live.

The annual calendar you're racing, and where a cure period actually exists

2027 9% LIHTC round — key dates (NH Housing's posted schedule, dates subject to change)
MilestoneDate
Financing application and exhibit lists postedMay 8, 2026
Pre-application period opensJune 3, 2026
Preliminary applications dueJuly 10, 2026, 5:00 PM
Staff distribute preliminary review memosAugust 21, 2026
Final applications dueSeptember 25, 2026, 5:00 PM
Board of Directors votes reservationsDecember 17, 2026

9% LIHTCs run one competitive round per year under this schedule. 4% credits paired with tax-exempt bonds are different: under HFA 109.04.G they aren't scored for a LIHTC allocation at all (bonds aren't volume-capped the way 9% credits are) and are accepted either on a rolling basis or through a published Notice of Funding Opportunity.

Unlike CTCAC's near-zero tolerance for late or missing threshold documents, HFA 109.05.C lets NH Housing, at its sole discretion, permit an applicant to immediately correct minor defects using a cure-period provision published in the Preliminary and Final Application Process Summary. That's a real, structural difference from California's regime. But a cure period fixes a defect in something submitted — it does not manufacture a document nobody ordered. The published exhibit list is still the actual gate.

The real diligence package arrives after you've already won — not before

Because the application itself asks for so little, the diligence documents California and Texas developers assemble before submitting show up in New Hampshire only after a reservation is already in hand, at three separate checkpoints in the QAP's appendices.

Progress Phase requirements (9% LIHTC), Appendix A — due within 120 days of reservation notification or 30 days before the carryover deadline, whichever is sooner
ExhibitRequirement
A.2Environmental site assessment and related reports (lead, asbestos, historic, archeological, if required by NH Housing)
A.3Appraisal — commissioned by NH Housing when it is the long-term lender, otherwise commissioned by the long-term lender with NH Housing named an intended user
A.7Evidence of continued site control, unless the property was owned at the time of application and a deed was already submitted
A.8Soils and/or structural engineering report, if applicable
A.13Dated evidence from the utility companies serving the site, confirming availability and capacity — dated within one year of the LIHTC reservation notification

The Progress Phase intro is explicit that missing these deadlines is not a soft failure: extensions are granted only "upon written request, and with good cause," at NH Housing's sole discretion, and "the tax credit reservation may be rescinded at the sole discretion of NH Housing for not meeting the progress phase requirements."

Site control gets checked twice more after that. Appendix B (Carryover Allocation Requirements, documents due by October 1 of the credit year) requires B.4, evidence of continued site control, again unless the property was already owned and deeded at application. Appendix C (Final Allocation Requirements — issuance of IRS Form 8609) requires C.11, a copy of the recorded deed or "comparable recorded site control." None of the three checkpoints (A.7, B.4, C.11) carries a QAP-specified freshness window of its own — the discipline this creates isn't clock math the way California's three title-report deadlines are, it's making sure the underlying option or PSA's own expiration date is engineered to survive all three dates on a single deal.

Title insurance is NH Housing's own job here — the survey is yours

Underwriting Standards Section 5.05.C states it in one line: "NH Housing's general counsel will handle all title insurance policy work." There is no QAP-set title-report freshness clock to track at all — nothing like California's simultaneous 90-day CTCAC / 90-day CDLAC / 30-day HCD MHP windows, and nothing like Texas's single six-month-with-bring-down-letter rule. A separate summary of closing insurance requirements is posted on NH Housing's website, and detailed requirements live in the project's regulatory agreement, but the QAP and underwriting standards do not publish a numeric deadline for how current a title report or commitment must be.

That absence is not the same as title diligence not mattering. A construction lender and an equity investor will still want their own current title work on their own schedule, and NH Housing's general-counsel process still has to clear before closing — it just means there is no state-published clock for a tool to enforce here the way there is in California or Texas.

The survey requirement, by contrast, is entirely the developer's. Underwriting Standards Section 5.06.C requires a site survey performed by a New Hampshire-licensed land surveyor for every property, and the standard is functional rather than a citation to a national convention: the survey and its affidavit must meet whatever is necessary to remove the survey exception from the title insurance policy. NH Housing spells out its own required elements — a north arrow, a legend, every building located, all easements burdening or appurtenant to the property, a complete metes-and-bounds boundary survey, springs/ponds/lakes/streams/rivers on or bordering the property, existing utilities, and "any other matters revealed by the title search" — rather than referencing ALTA/NSPS Table A items by name the way both the California and Texas practice does.

Appraisal sets a price ceiling, and who orders it depends on who's lending

Underwriting Standards Section 5.06.A: "Acquisition costs which exceed the appraised value are generally not eligible to be financed using NH Housing funds, except under extenuating circumstances with NH Housing approval. The acquisition price is limited to the lesser of the sale price or appraised value." The appraisal itself must comply with USPAP. Who commissions it depends on what NH Housing is providing: when NH Housing is the long-term amortizing first-mortgage lender, NH Housing commissions the appraisal directly; when it's only providing a deferred payment loan or construction financing, it relies on the report the long-term lender commissioned, provided NH Housing is listed as an interested party or intended user.

This is a different kind of rule than California's appraisal-date-versus-site-control-execution-date window. NH Housing's rule isn't a timing window at all — it's a price ceiling. The check a tool needs to run in New Hampshire is not "is the appraisal dated within X days of the option," it's "does the acquisition line in the development budget exceed the appraised value," and that check applies to every acquisition NH Housing finances, not only identity-of-interest transactions.

Two Phase I clocks, for two different purposes, that do not agree with each other

Underwriting Standards Section 5.06.B makes a Phase I Environmental Site Assessment mandatory for every NH Housing-financed project, conforming to "the most recent edition of the ASTM Standard Practice for Environmental Site Assessments: Phase I ESA Process" — a forward-looking reference rather than naming a specific edition that can go stale on the page.

Within 1 year of the report's effective datePhase I "current" for financing
A letter updating five named components is required instead of a new report180 days–1 year lapsed
An entirely new Phase I must be obtained1 year or more lapsed

The five components that must be refreshed in that update letter — interviews with past and present owners/operators/occupants, searches for recorded environmental cleanup liens, review of federal/tribal/state/local government records, visual inspection of the facility and adjoining properties, and the environmental professional's declaration — are lifted almost verbatim from the federal All Appropriate Inquiries rule's own refresh list at 40 CFR §§ 312.23, 312.25, 312.26, 312.27, and 312.21. That's a genuinely different design choice than California's: CTCAC's separate 12-month clock (keyed to the application deadline) and the federal AAI clock (keyed to the acquisition date) routinely diverge in California's own guide. In New Hampshire, NH Housing built its financing-currency test directly out of AAI's own 180-day/1-year windows, so there is only one clock to track for this purpose, not two that quietly drift apart.

That one clock is not, however, the only Phase I clock running on a New Hampshire deal. Separately, at application, the QAP's Advanced Projects scoring category (HFA 109.07) awards 3 bonus points for "Phase 1 Environmental completed," and its own documentation column defines that as a report "dated within five years" — but adds, in the same cell, that "a new Phase 1 ESA will be required if the project receives a reservation." So a five-year-old report can legitimately earn scoring points at application and still be entirely unusable nine months later at Progress Phase under the one-year financing-currency test. The two clocks are never reconciled anywhere in the QAP text — treat them as serving two different purposes, not as the same requirement stated twice.

There is also a third, state-agency-driven environmental step that happens automatically and is easy to conflate with the developer's own Phase I: under HFA 109.05.A, submitting a preliminary application and letter of intent for a 9% round triggers NH Housing itself to commission an abbreviated HUD Environmental Checklist from a third-party professional it selects, at a fee payable directly to that vendor. Any issues the checklist raises must be discussed with NH Housing staff. It is a narrower screening tool with its own separate fee, not a substitute for the developer's own Phase I ESA.

Federal money layers its own review on top of all of this. For HOME-, Project-Based Voucher-, or FHA Risk Share-funded projects, the appropriate 24 CFR Part 58 HUD Environmental Checklist must be submitted to HUD (by NH Housing) for a release of funds before loan closing can occur — the same choice-limiting-activity logic California and Texas both face. Federal Housing Trust Fund money runs a separate environmental review under 24 CFR § 93.301(f) that, per NH Housing's own standards, does not require a release of funds from HUD.

Local site plan approval has its own finality test — "approved" can still mean "not done"

Threshold A, HFA 109.06.A, requires the proposed project to have been granted site plan approval before final application. That takes more than a Notice of Decision: the applicant must also submit a permit-status letter from the project engineer or sponsor's attorney confirming the approval meets the requirements of RSA 676:4, I(i), naming the dates each separate local approval (Planning, Zoning, Historical, Conservation, and/or other) was granted, and narrating how any conditions — including expiration — were satisfied.

RSA 676:4, I(i) governs when a conditionally-approved plat or site plan actually becomes final. It becomes final, without a further public hearing, only once every condition falls into one of a narrow set of categories — minor administrative plan modifications, other conditions requiring no discretionary board judgment, or conditions tied to obtaining a permit or approval from another government agency. Any condition outside those categories requires a full new public hearing with proper notice before the approval is final. A developer holding a locally-issued "conditional approval" that hasn't cleared that bar does not satisfy Threshold A, however confident the planning department sounds about it.

One drafting inconsistency worth flagging rather than treating as settled: the QAP's own table of contents still lists a standalone "K. Environment" threshold subsection under HFA 109.06 Threshold Criteria. The body of the March 16, 2026 QAP has no such section — its actual subsection K is "Smoke Free Requirement." That means the current QAP has no standalone environmental threshold criterion at the application stage at all, only the automatically-commissioned HUD checklist and the optional Advanced Projects scoring bonus described above. Confirm this against whatever amendment, if any, follows before relying on it — a table of contents that hasn't caught up with the body text is a live artifact, not a citation.

New Hampshire land-use overlays that change what you can build, or what you owe at closing

State permitting and tax regimes that bear on site diligence
RegimeWhat it requiresCitation
Wetlands dredge-and-fill permit"No person shall excavate, remove, fill, dredge, or construct any structures in or on any bank, flat, marsh, or swamp in and adjacent to any waters of the state without a permit" from NH DES. The department must issue an administrative-completeness notice within 10 days; it then has 50 days (projects under 1 acre) or 75 days (larger projects) to approve, deny, or schedule a hearing, with a permit-by-default mechanism if it misses its own deadline.RSA 482-A:3
Shoreland Water Quality Protection ActRegulates all "protected shoreland" within 250 feet of the reference line of public waters (50 feet for certain river segments): a 50-foot primary-structure setback, a 50-foot waterfront buffer, a 150-foot woodland buffer with vegetation-maintenance requirements, soil-dependent septic setbacks of 75–125 feet, and impervious-surface thresholds (engineered stormwater management required above 30% of the lot's protected-shoreland area, infiltration requirements above 20%).RSA 483-B:4, :9
Alteration of Terrain permitA permit is required before dredging, excavating, filling, mining, or otherwise significantly altering terrain; detailed plans must be submitted at least 30 days before the activity begins, with a tiered fee schedule based on disturbed square footage.RSA 485-A:17
Current Use Land Use Change TaxA one-time tax of 10% of the land's full and true market value — not its discounted current-use value — becomes due when land enrolled in New Hampshire's current-use (open space/forestland) assessment program is converted to a non-qualifying use, including the start of construction.RSA 79-A:7

The Alteration of Terrain statute sets the permitting process and fee tiers but does not itself state the disturbed-area threshold that triggers the requirement — that lives in the department's own administrative rules, not read for this guide. Confirm the current threshold with NH DES rather than assuming a number.

The Land Use Change Tax is the least visible of these and the easiest to miss on a rural acquisition: a parcel's low assessed value on the tax card can be an artifact of its current-use enrollment, and the 10%-of-full-market-value bill lands the moment site work starts, not at closing — a cost that has to be underwritten into the acquisition budget, not discovered at the tax collector's office.

A buildable envelope that turns out to sit inside the 483-B protected-shoreland zone without anyone checking early enough is the New Hampshire equivalent of California's Alquist-Priolo trap: the 50-foot setback and 150-foot woodland buffer can remove enough developable land to break the unit count the pro forma was built on, and it surfaces late if the wetlands and shoreland checks aren't run before the design is set.

On relocation: NH Housing's Anti-Displacement and Relocation Policy (Underwriting Standards § 2.13) requires full compliance with the federal Uniform Relocation Assistance and Real Property Acquisition Policies Act for projects using HOME or Housing Trust Fund money, and a relocation plan plus all required tenant notices must be submitted with the application if any relocation is anticipated. The research behind this guide did not turn up a New Hampshire state-law relocation-assistance regime layered on top of federal URA the way California's Government Code § 7260 layers onto federal law generally for LIHTC deals — treat that as an open question to confirm with counsel on any occupied acquisition site, not as a settled "there is no such law."

Where this goes wrong

  • Reading Threshold F's two sentences as meaning site control barely matters here. It sets no freshness or minimum-term rule, but Progress Phase, Carryover, and Final Allocation each independently re-check "continued site control" (Exhibits A.7 and B.4), and NH Housing can rescind a reservation at its sole discretion for missing a Progress Phase deadline.
  • Assuming NH Housing runs a title-freshness clock the way CTCAC or TDHCA do, and therefore not lining up a construction lender's or equity investor's own title timeline early — NH Housing's general counsel handling title work is not a substitute for the developer's own diligence schedule, and no QAP-published deadline exists to fall back on.
  • Ordering a Phase I ESA to satisfy the QAP's five-year Advanced Projects scoring bonus and assuming it's also good for financing. Underwriting Standards require a Phase I "current" within one year of its effective date (with a 180-day-to-one-year update-letter window), and a brand-new Phase I is required outright once the project actually wins a reservation.
  • A Phase I sits for 180-plus days without anyone ordering the five-component AAI-style update letter (interviews, lien search, records review, visual inspection, EP declaration), and by Progress Phase the report has quietly gone stale.
  • Treating a locally "approved" site plan as final when it's still conditionally approved outside RSA 676:4, I(i)'s narrow categories — Threshold A requires a permit-status letter confirming true finality, not a Notice of Decision with open conditions still outstanding.
  • Missing the Land Use Change Tax under RSA 79-A:7 — a 10% hit on the property's full market value, not its current-use value, the moment site work starts on a current-use-enrolled parcel, an acquisition cost nobody budgeted because the assessed value on the tax card looked low.
  • Starting terrain-disturbing work without the RSA 485-A:17 Alteration of Terrain permit's required 30-day advance notice to NH DES, or without confirming the disturbed-area threshold that actually triggers the requirement, since it isn't stated in the statute itself.
  • A buildable envelope that turns out to sit inside RSA 483-B's 250-foot protected shoreland without anyone checking early — the 50-foot primary-structure setback and 150-foot woodland buffer can remove enough developable area to break the unit count the pro forma assumed.
  • Assuming NH Housing's automatically-commissioned abbreviated HUD Environmental Checklist (triggered by the preliminary application/LOI) substitutes for the developer's own Phase I ESA — it's a separate, narrower screening step with its own fee, not a substitute.
  • Citing the QAP's own table of contents, which still lists a "K. Environment" threshold subsection that no longer exists in the current document body — a live drafting inconsistency in the March 16, 2026 QAP, not a stable citation to build a checklist around.
  • Missing that the RSA 482-A wetlands permit runs its own NH DES review clock (a 10-day completeness check, then 50 or 75 days to decide) that has nothing to do with NH Housing's own application calendar, and can still be pending when the LIHTC deadline arrives.
  • Assuming the appraisal-price ceiling only applies to related-party purchases — Underwriting Standards § 5.06.A caps acquisition cost at the lesser of price or appraised value on every deal NH Housing finances, not only identity-of-interest ones.
  • An occupied structure on an acquisition/rehab site triggers federal URA obligations on a HOME- or HTF-funded deal, and this guide's research did not confirm a parallel New Hampshire relocation-assistance statute the way California layers one on top of URA — verify with counsel rather than assuming either way.
  • Real diligence money spent on a site secured only by a bare LOI with no extension mechanism built in, discovered mid-cycle when the seller has other offers — because 9% LIHTC runs one competitive round a year here, there is no second chance until next year's schedule.

At a glance

Allocating agency
New Hampshire Housing Finance Authority ("NH Housing"), created under RSA Chapter 204-C
Current QAP
Effective March 16, 2026, covering the 2027–2028 LIHTC cycle (HFA 109)
2027 9% round dates
Preliminary applications due July 10, 2026; final applications due September 25, 2026; Board vote December 17, 2026
Site control threshold
HFA 109.06.F — "secure site control" via option, lease agreement, or other legal form; no QAP-specified minimum term or freshness window
Progress Phase deadline
Within 120 days of reservation notification, or 30 days before the carryover deadline, whichever is sooner
Carryover documents due
October 1 of the credit year
Phase I financing-currency test
Current = within 1 year of effective date; 180 days–1 year lapsed requires a 5-component update letter; 1+ year requires a new Phase I
Phase I scoring bonus (separate clock)
3 points for a report dated within 5 years — but a new Phase I is required if the project wins a reservation (HFA 109.07, Advanced Projects)
Appraisal rule
Acquisition price capped at the lesser of contract price or appraised value; USPAP compliance required (Underwriting Standards § 5.06.A)
Site survey
Required for all NH Housing-financed properties, by an NH-licensed surveyor, sized to remove the survey exception from the title policy (§ 5.06.C)
Title insurance
Handled directly by NH Housing's own general counsel (§ 5.05.C) — not a QAP-mandated developer submittal with a set freshness window
Protected shoreland (RSA 483-B)
250 ft from the reference line; 50-ft primary-structure setback; 150-ft woodland buffer; 75–125 ft septic setback
Current Use Land Use Change Tax
10% of the property's full market value, triggered when current-use land converts to a non-qualifying (developed) use — RSA 79-A:7
Alteration of Terrain permit
Plans required at least 30 days before construction begins — RSA 485-A:17
Wetlands permit review clock
10-day completeness notice; then 50 days (under 1 acre) or 75 days (larger) to decide — RSA 482-A:3

Governing authority

  • NH Housing's enabling statuteRSA Chapter 204-C
  • Site control thresholdHFA 109.06.F, NH Housing Qualified Allocation Plan, effective March 16, 2026
  • Site plan approval threshold and finality requirementHFA 109.06.A; RSA 676:4, I(i)
  • Preliminary application / NH Housing-commissioned HUD Environmental ChecklistHFA 109.05.A
  • Application submission and cure-period provisionHFA 109.05.C
  • Advanced Projects scoring — Phase I bonus and new-Phase-I-on-reservation conditionHFA 109.07, Advanced Projects scoring category
  • Tax-Exempt Bonds combined with 4% LIHTC — rolling/NOFO acceptance, not scored for allocationHFA 109.04.G
  • Amendments to the QAP — Board of Directors and Governor approvalHFA 109.11.E
  • Progress Phase Requirements (9% LIHTC) — environmental, appraisal, continued site control, utility evidenceQAP Appendix A, Exhibits A.2, A.3, A.7, A.8, A.13
  • Carryover Allocation Requirements — continued site controlQAP Appendix B, Exhibit B.4
  • Final Allocation Requirements (Form 8609) — recorded deed or comparable recorded site controlQAP Appendix C, Exhibit C.11
  • 2027 9% LIHTC application scheduleNH Housing, Application Schedule for 2027 9% Low-Income Housing Tax Credits (published under HFA 109.05.B)
  • Title insurance handled by NH Housing's general counselNH Housing Underwriting Standards and Development Policies for Multifamily Finance (eff. July 10, 2024), § 5.05.C
  • Appraisal — acquisition price ceiling and commissioning ruleNH Housing Underwriting Standards, § 5.06.A
  • Environmental — Phase I ESA currency test and HUD/HTF reviewNH Housing Underwriting Standards, § 5.06.B
  • Site survey requirementNH Housing Underwriting Standards, § 5.06.C
  • Anti-Displacement and Relocation PolicyNH Housing Underwriting Standards, § 2.13
  • Federal All Appropriate Inquiries — refresh components mirrored in NH's Phase I currency test40 CFR §§ 312.20, 312.21, 312.23, 312.25, 312.26, 312.27
  • HUD environmental review / release of funds24 CFR Part 58
  • Housing Trust Fund environmental review24 CFR § 93.301(f)
  • Federal Uniform Relocation Assistance and Real Property Acquisition Policies Act42 U.S.C. § 4601 et seq.; 49 CFR Part 24
  • QAP public-hearing / elected-official approval requirement (federal baseline)IRC § 42(m)(1)(A)(i)
  • Wetlands dredge-and-fill permitRSA 482-A:3
  • Shoreland Water Quality Protection Act — definitions and minimum standardsRSA 483-B:4, 483-B:9
  • Alteration of Terrain permitRSA 485-A:17
  • Current Use Land Use Change TaxRSA 79-A:7

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.