Skip to content

Cost, construction type and the labor package — New Hampshire

Phase 6 of 11

"What does this actually cost, and does NH Housing's own dollar cap let it pencil?"

Not yet coveredWeeks to months

Four passes, and the locked number is a dollar cap, not a limit table

Cost estimation in a New Hampshire LIHTC deal follows the same four-pass structure every LIHTC state uses, but what gets locked, and against what, differs from both California and Texas. There is no county-by-county basis-limit table here — the number a New Hampshire application is tested against is a single, statewide dollar figure computed from the project's own unit count and bedroom mix.

The four cost-estimating passes, New Hampshire
PassWho produces it / NH Housing documentPrecisionTiming
Napkin / screening estimateDeveloper's own model, in Excel±30–40%Minutes to hours
Concept estimateArchitect's schematic design (SD) set, priced informally by a GC or estimator±15–20%Weeks after schematic design
Preliminary and final application budgetDeveloper plus LIHTC consultant, entered in NH Housing's financing application and tested against the TDC Weighted AverageLocked for the funding roundPreliminary application / Letter of Intent (minimum requirements posted by May 1 each year), then the final application
GMP or final cost certificationGC or CM pricing under HFA 111 procurement rules; certified by a CPA at 8609 issuance±3–5%, then audited10% test within 12 months of the Carryover Allocation Agreement; final cost certification at close-out

New Hampshire's readiness threshold makes the application-stage number more disciplined than a pure napkin figure. To be considered complete, an application must already include a detailed scope of work with cost estimates current within six months, plus schematic design plans and specifications — so the number NH Housing tests is closer to a concept estimate than a back-of-envelope one, even at the earliest competitive round.

Who is actually in the room mirrors California's list minus one role: developer project manager, architect, GC or CM preconstruction estimator, and LIHTC consultant. A labor compliance consultant only enters the picture if a federal program in the capital stack triggers Davis-Bacon — New Hampshire itself has no state prevailing-wage apparatus to staff for.

One structural question the QAP text does not resolve: whether the TDC Weighted Average ceiling is re-tested at placed-in-service, the way CTCAC re-tests California's high-cost limit against a revised, placed-in-service-year figure. The closeout package visible in the QAP (Appendix C) calls for a CPA-certified final cost certification checked for consistency with the application's Sources and Uses — that reads as a consistency check, not an explicit second pass against the $397,000/$425,000 ceiling, but the QAP does not say so outright. Confirm the actual mechanics with NH Housing's Construction Services Manager before assuming California's pattern carries over.

The TDC Weighted Average is the spine of the phase

Where CTCAC tests eligible basis against a threshold basis limit table keyed to county and bedroom count, NH Housing tests total development cost against a single blended formula, evaluated against three flat dollar ceilings that apply the same way whether the project sits in Manchester or Colebrook.

The formula and the three dollar ceilings it feeds
CeilingApplies toAmount
TDC Weighted Average, standardAll projects not qualifying for the high-cost category$397,000
TDC Weighted Average, high-costProjects meeting at least one of seven enumerated high-cost criteria$425,000
Total development cost per unit, unweightedEvery project, regardless of high-cost status$464,000
Investment limit (NH Housing capital subsidy + LIHTC equity)Per unit, all projects (evaluated case-by-case below 30% AMI)$315,000

TDC Weighted Average = ([2 × TDC/unit] + [TDC/bedroom]) ÷ 3. For mixed-use projects, only the residential portion, including common areas, is used. Applications that miss the applicable ceiling are rejected absent an approved HFA 117 waiver.

There is no regional variation in the base formula. Unlike CTCAC's per-county, per-bedroom threshold basis limit table, New Hampshire runs one statewide number for every county from Coos to Rockingham. The QAP's only nod to geography is the high-cost county carve-out below — a binary yes-or-no by county, not a continuous regional coefficient like Terner Center's California figures.

The seven high-cost qualifying criteria — the $28,000-per-unit ceiling swing
CriterionDocumentation
Adaptive reuse projectThorough supporting documentation submitted with the application
Uses Historic Rehabilitation Tax CreditsSame
Site meets the EPA's brownfield definitionSame
Required to comply with the Build America, Buy America Act (BABA)Same — see the labor package section below
Designed and built to achieve Passive House certificationSame — also earns 2 scoring points under HFA 109.07
Faces an inadequate bidder pool, impeding a competitive bid processSame
Located in Grafton, Carroll, or Coos CountySame

Meeting one of the seven raises the ceiling from $397,000 to $425,000 — a $28,000-per-unit swing on a formula NH Housing applies unit by unit. The application must submit thorough evidence, and NH Housing decides eligibility on review, not the developer at budgeting time.

The BABA criterion is the one most likely to appear or disappear without the developer choosing it. Applicants may not request a specific NH Housing capital subsidy source, and the QAP instructs applicants to assume the most restrictive one — typically HOME, which carries Build America, Buy America Act compliance. If BABA turns out not to be required, the project drops out of the high-cost category (back to the $397,000 ceiling) unless it qualifies on another ground; NH Housing has discretion to grant an exception to that reclassification.

The investment limit is evaluated once, at application, using projected equity pricing and NH Housing subsidy — a later equity-pricing swing does not by itself trigger a re-evaluation. That is real, stated protection against LIHTC equity market volatility between application and closing.

Cost reasonableness is tested twice: a hard cap, then a moving target

New Hampshire runs two separate cost tests out of two separate parts of the QAP, and they behave differently. One is a fixed threshold that either passes or fails an application outright. The other is a competitive, relative penalty that a developer cannot fully price until the round's other applications are in.

Two different cost tests, two different documents
TestWhere it livesMechanismConsequence
Hard ceilingHFA 109.06.G Cost Reasonableness / HFA 109.04.CTDC Weighted Average (or unweighted per-unit cost) exceeds the applicable $397,000 / $425,000 / $464,000 figureApplication rejected, absent an approved HFA 117 waiver
Relative penaltyHFA 109.07 Scoring, Item 11 (Project Cost)Project's TDC Weighted Average compared to the average of all TDC Weighted Averages submitted in the current roundNegative scoring points, on a sliding scale
The scoring penalty ladder (Item 11)
Over the round average by...Negative points
5% (meets no high-cost criteria)-2
10% (meets no high-cost criteria)-4
25% (meets no high-cost criteria)-6
10% (meets one high-cost criterion)-2
10% (meets two or more high-cost criteria)0

Preservation/recapitalization projects are excluded from this scoring category and from the round-average calculation.

The second test is the harder one to underwrite to, because it is relative. A developer can sit comfortably under the $397,000 hard ceiling and still take a scoring hit if every other application in that round happens to come in lean — the benchmark is this round's own peer group, not a fixed figure published in advance. That is a genuinely different risk shape than California's high-cost test, where 30% over a published, county-specific limit is knowable the moment the year's limit memo is out.

A waiver against the hard ceiling runs through the HFA 117 Waiver Rules process — a real but discretionary path, not a formula. Treat it as an exception mechanism, not a planning assumption.

No construction-type basis-boost menu — cost relief runs through project type and geography instead

This is the sharpest structural difference from California in the whole phase. CTCAC ties basis-limit boosts directly to physical construction type and story count — Type I versus Type III, elevator-served upper floors, parking below grade. New Hampshire's QAP does none of that. There is no construction-type basis bump, no story-count trigger, and no menu of percentage boosts stacked on a base limit. The only levers that move a New Hampshire cost ceiling are the seven high-cost criteria above.

New Hampshire's building code baseline sits underneath all of this without feeding directly into LIHTC cost limits the way California's does. The state building code, administered by the State Building Code Review Board, currently adopts the 2021 International Building Code (with the 2018 International Energy Conservation Code as the energy baseline). Story and construction-type limits under that code still shape a project's design and cost — but unlike CTCAC's regulation, New Hampshire's QAP does not reference them, index a basis boost to them, or otherwise make them a scored or gated item.

Energy-efficient design scoring items that double as high-cost qualifiers
ItemRequirementPoints
16.bPassive House certification2
16.b (alternative)HERS 47 or better (no solar) / HERS 24 or better (with qualifying solar)2

Only the Passive House path — not the HERS-alone path — appears on the seven-item high-cost list. Achieving a HERS 24 or 47 target earns scoring points but does not, by itself, raise the cost ceiling to $425,000.

That overlap is worth underwriting deliberately: a developer chasing the 2 scoring points for Passive House certification simultaneously unlocks $28,000 per unit of cost-ceiling headroom, which a HERS-only compliance path does not. Two different documents (the scoring criteria and the high-cost criteria list) reward the same design decision for two different reasons, and only one path pays both.

The labor package is almost entirely a federal question, because New Hampshire has none of its own

New Hampshire has no state prevailing-wage law. RSA Chapter 280, "Minimum Wages of Employees in Public Works," New Hampshire's own little-Davis-Bacon statute, was repealed in its entirety by Laws 1985, 117:1, effective July 13, 1985, and nothing has replaced it. Compare that to California's Labor Code §1720 machinery — the broad public-funds trigger, the six subcategories that catch donated land and below-market loans, the strict judicial construction of the narrow exemptions. In New Hampshire, that entire layer of cost and compliance risk simply does not exist at the state level.

Federal Davis-Bacon triggers by program — the only labor-standards layer that reaches a New Hampshire deal
ProgramTriggerCitation
HOME12 or more HOME-assisted units in the construction contract24 CFR §92.354
CDBGRehabilitation of residential property with 8 or more units24 CFR §570.603
Project-based Section 8New construction or substantial rehabilitation at 9 or more assisted unitsHUD labor-standards guidance — confirm against HUD Handbook 1344.1 for a specific deal
Public Housing (1937 Act)No unit thresholdHUD labor-standards guidance — same caveat
NAHASDANo unit threshold; $2,000 contract thresholdHUD labor-standards guidance — same caveat

The HOME and CDBG thresholds are read directly from the current Code of Federal Regulations. The Section 8, Public Housing and NAHASDA rows are standard HUD program thresholds carried from general HUD guidance; verify the exact figure against HUD Handbook 1344.1 before relying on it for a specific deal.

BABA is a second, separate federal layer, and it is a materials rule, not a wage rule. The Build America, Buy America Act requires domestic sourcing of iron, steel, manufactured products and construction materials on projects funded with covered federal financial assistance — it does not set a wage floor the way Davis-Bacon does. It reaches a New Hampshire deal the same way Davis-Bacon does: through whichever HOME, HTF or other federal capital-subsidy dollars NH Housing puts into the stack, which is exactly why the QAP folds BABA compliance into its high-cost criteria list rather than treating it as a labor-standards item.

HUD Section 3 — economic-opportunity and hiring-preference requirements for residents of HUD-assisted housing and low-income area residents — shows up in NH Housing's own Underwriting Standards as a required competency area for the owner's representative, alongside Davis-Bacon and BABA. It is a contracting and hiring-preference obligation for HUD-funded projects, not a wage-rate rule, but it is a real compliance and administrative cost that a purely materials-and-wages view of "the labor package" will miss.

The practical upshot: a New Hampshire deal financed with LIHTC equity, a conventional first mortgage, and NH Housing's own state-funded Affordable Housing Fund — no HOME, HTF, CDBG or project-based Section 8 in the stack — can plausibly clear this entire phase with zero Davis-Bacon exposure. That is close to structurally impossible on a Southern California 9% deal, where Terner Center's own data puts prevailing-wage prevalence at 52.6% of 2020–2023 California LIHTC awards. Whether a specific New Hampshire deal clears it depends entirely on which capital-subsidy dollars end up in the stack, which is exactly why the QAP tells applicants to assume the worst case until financing is locked.

The structural caps that bind the budget, and the order to run this in

Builder overhead, profit and general conditions cap
Cost of the WorkCombined OH&P + general conditions cap
$3,000,000 or more14%
$1,300,000 to $3,000,00016%
$1,300,000 or less20%

Excludes performance/payment bonds and building permits. Applies under General Contracting, Construction Management, or Design-Build delivery alike.

Developer fee schedule (effective July 10, 2024)
Unit tierGeneral occupancyAge-restricted
First 10 units$23,760/unit$21,600/unit
Next 30 units$19,440/unit$17,280/unit
Next 60 units$16,200/unit$14,580/unit
Above 100 units$7,020/unit$7,020/unit

Capped overall at 15% of total development cost. Acquisition-only deals (rehab/new construction under 50% of TDC, not counting land) use a flat $6,300/unit instead. Tax-exempt bond 4% deals may take up to 15% of TDC, but any amount above what the per-unit schedule would otherwise allow must be loaned back to the project as a developer fee loan.

Where there is an identity of interest between the builder and the developer, a second cap stacks on top of the schedule above: the combined developer fee plus builder overhead, profit and general conditions may not exceed 18% of total development cost on projects with construction costs above $2.5 million, or 20% at or below $2.5 million. Separately, HFA 111.12 does not permit an identity-of-interest Construction Manager or General Contractor to participate by default — it requires a written request and case-by-case approval from NH Housing's Executive Director, a self-contained gate inside HFA 111 itself, not the HFA 117 Waiver Rules process used for the QAP's own cost ceilings.

Two different contingency numbers get conflated in practice. The developer's own construction contingency is 5% of the construction amount for new construction and 10% for rehabilitation, under the Underwriting Standards. The Construction Manager's own GMP contingency, a separate figure inside the CM's fee structure, is capped at 3.5% and may not be used to supplement general conditions or self-performed work. They live in two different documents and answer two different questions.

Bids over budget trigger a defined process, not a quiet adjustment. A GMP or bid within 10% of the application budget can be negotiated with the low bidder subject to design-team and NH Housing approval. Anything over 10% forces a meeting among the developer, architect, low bidder and NH Housing, and NH Housing can compel a redesign and re-bid at its discretion — a real schedule and cost consequence for a budget that was priced thin at application.

Modular construction gets a defined procurement rule and nothing else. Projects using modular construction must obtain three competing bids from modular contractors, the same competitive-bidding discipline applied to any other subcontractor. Neither the QAP nor the Underwriting Standards publish a modular cost-savings benchmark — the same gap California's own research corpus flags, and for the same reason: no controlling state-specific study appears to exist yet.

Two more real soft-cost lines are easy to underbudget: the LIHTC Allocation Fee runs 7% of the total LIHTC allocation amount (1% due with the application, 6% due with the final allocation package, before IRS Form 8609 is issued), and the LIHTC Upfront Monitoring Fee is a flat per-unit charge — $675 per unit for 4% LIHTC projects, $850 per unit for 9% LIHTC projects — due with the final allocation package, and does not vary by the LURA's affordability-period length.

The order to run this in
StepActionWhy
1Fix the unit mix and get at least a current (within 6 months), SD-level cost estimateBoth are readiness-threshold requirements before an application is even considered complete
2Run the TDC Weighted Average formula and honestly test each of the seven high-cost criteria before assuming any of them applyA $28,000-per-unit ceiling swing turns on documentation NH Housing reviews after the fact, not on the developer's own judgment at budgeting time
3Identify the likely capital stack and price Davis-Bacon/BABA exposure at the most restrictive assumption (HOME) until financing is lockedThe QAP itself instructs this; pricing zero labor-standards exposure because the subsidy source isn't picked yet inverts the QAP's own guidance
4Size the developer fee off the correct per-unit schedule (general occupancy vs. age-restricted) and check the identity-of-interest 18%/20% cap separatelyThese are two different caps that bind independently of each other
5Underwrite to the round-average scoring penalty, not just the hard ceilingBeing under $397,000 does not protect against losing points to a round where the competition costs less

Where this goes wrong

  • Treating the $397,000 TDC Weighted Average as a target to approach rather than a hard ceiling. Going even modestly over it without an approved HFA 117 waiver means automatic rejection under HFA 109.06.G, not a negotiation with staff.
  • Underwriting only to the fixed dollar ceiling and ignoring the separate scoring penalty. A project safely under $397,000 per the weighted formula can still lose 2 to 6 points if the round's other applicants come in leaner — the benchmark is this round's own average, not a number published in advance.
  • Assuming a high-cost criterion applies without documenting it. The QAP requires thorough evidence for each of the seven criteria, reviewed and approved by NH Housing after submission — budgeting to the $425,000 ceiling because a site 'probably' counts as a brownfield or bidder pool is 'probably' inadequate is not the same as having it approved.
  • Pricing zero Davis-Bacon or BABA exposure because the NH Housing capital subsidy source hasn't been selected yet. The QAP explicitly instructs applicants to assume the most restrictive source (typically HOME) until financing commitment — the opposite assumption inverts the QAP's own guidance and can leave a real cost surprise sitting in the stack.
  • Importing a California-style prevailing-wage cost premium into a New Hampshire pro forma. New Hampshire repealed its own public-works wage law (RSA 280) in 1985; absent a federal Davis-Bacon trigger from HOME, CDBG, project-based Section 8, Public Housing, or NAHASDA funding, there is no state-level wage floor to price at all.
  • Signing a construction contract with an identity-of-interest general contractor or construction manager without NH Housing's prior approval. HFA 111.12 requires a written request and case-by-case approval by NH Housing's Executive Director before an affiliated GC or CM may participate at all; discovering that after running a full procurement process with the developer's own affiliated GC wastes the cycle.
  • Conflating the Construction Manager's own 3.5% GMP contingency cap with the developer's overall construction contingency of 5% (new construction) or 10% (rehabilitation). They are two different numbers in two different documents, and using one where the other belongs misstates the available cushion.
  • Treating a GMP that comes in 10%+ over the application budget as routine value engineering. HFA 111.11(b) requires the developer, architect, low bidder, and NH Housing to meet, and NH Housing can compel a redesign and re-bid — a real schedule and cost consequence, not a formality.
  • Sizing the developer fee off the wrong per-unit tier. General-occupancy and age-restricted projects run different per-unit schedules, and an identity-of-interest deal with construction costs above $2.5 million caps the combined developer fee plus builder OH&P at 18% of total development cost (20% below $2.5 million) on top of that schedule.
  • Building a modular cost case on manufacturer marketing claims. New Hampshire's rules specify a bidding procedure for modular construction (three competing modular-contractor bids) but publish no modular cost-savings benchmark — the same gap California's own research corpus flags.
  • Leaving the LIHTC allocation fee and the per-unit upfront monitoring fee out of the soft-cost budget. At 7% of the total LIHTC allocation (1% at application, 6% at final allocation) plus a flat $675 (4% LIHTC) or $850 (9% LIHTC) per unit, these are real, sizable NH Housing fees, not rounding errors.
  • Assuming the TDC Weighted Average is re-tested against the same ceiling at placed-in-service the way California's high-cost test is. The QAP does not clearly state a placed-in-service re-test against the $397,000/$425,000 figures — confirm the actual closeout mechanics with NH Housing's Construction Services Manager rather than assuming CTCAC's pattern carries over.

At a glance

Allocating agency
NH Housing (New Hampshire Housing Finance Authority)
Current QAP effective date
March 16, 2026 (HFA 109)
TDC Weighted Average formula
([2 × TDC/unit] + TDC/bedroom) ÷ 3
TDC Weighted Average ceiling, standard
$397,000
TDC Weighted Average ceiling, high-cost
$425,000 (7 qualifying criteria)
Total development cost per unit, hard cap
$464,000, unweighted, all projects
Investment limit (subsidy + LIHTC equity)
$315,000 per unit; case-by-case below 30% AMI
Cost scoring penalty (over round average)
-2 to -6 points at 5%/10%/25% over average
Builder OH&P + general conditions cap
14% (≥$3M) / 16% ($1.3M–$3M) / 20% (≤$1.3M) of Cost of the Work
Developer construction contingency
5% new construction / 10% rehabilitation
CM's own GMP contingency cap
3.5%, separate from the developer's contingency
Developer fee (general occupancy, first 10 units)
$23,760/unit; overall cap 15% of TDC
Identity-of-interest fee + OH&P combined cap
18% of TDC (construction >$2.5M) / 20% (≤$2.5M)
LIHTC Allocation Fee
7% of total LIHTC allocation (1% at application, 6% at final)
State prevailing wage law
None — RSA 280 repealed by Laws 1985, 117:1, eff. 7/13/1985
Federal Davis-Bacon trigger, HOME
12 or more HOME-assisted units (24 CFR §92.354)
Federal Davis-Bacon trigger, CDBG
Residential rehab of 8 or more units (24 CFR §570.603)
Max 9% LIHTC per project
$942,000 general occupancy / $706,000 age-restricted

Governing authority

  • Per-unit cost standards and housing investment limitsNew Hampshire Qualified Allocation Plan (HFA 109), Section 109.04.C, effective March 16, 2026
  • Developer fee cross-reference in the QAPNH QAP (HFA 109), Section 109.04.E
  • Cost reasonableness thresholdNH QAP (HFA 109), Section 109.06.G
  • Project cost scoring penaltyNH QAP (HFA 109), Section 109.07, Scoring Item 11
  • Basis boost (130% for DDA/QCT)NH QAP (HFA 109), Section 109.04.F
  • Readiness threshold — current cost estimates and SD plans requiredNH QAP (HFA 109), Section 109.06.H
  • Energy-efficient design scoring (Passive House / HERS)NH QAP (HFA 109), Section 109.07, Scoring Item 16
  • Maximum 9% LIHTC allocation per projectNH QAP (HFA 109), Section 109.04.A
  • Developer fee schedule and identity-of-interest fee capNH Housing, Underwriting Standards and Development Policies for Multifamily Finance, Section 5.02.B, effective July 10, 2024
  • Construction contingencyNH Housing, Underwriting Standards and Development Policies for Multifamily Finance, Section 5.05.B
  • Builder's fees cross-reference to HFA 111NH Housing, Underwriting Standards and Development Policies for Multifamily Finance, Section 3.01
  • Owner's representative labor-standards competency (Davis-Bacon, BABA, Section 3)NH Housing, Underwriting Standards and Development Policies for Multifamily Finance, Section 4.06
  • Builder overhead, profit and general conditions sliding capNH Housing, HFA 111 Design and Construction Policy Rules, Section 111.07(d)-(f), effective June 15, 2024
  • Construction Management GMP contingency cap and modular bidding requirementNH Housing, HFA 111 Design and Construction Policy Rules, Section 111.08(b) and (g)
  • Bids over budgetNH Housing, HFA 111 Design and Construction Policy Rules, Section 111.11
  • Identity of interestNH Housing, HFA 111 Design and Construction Policy Rules, Section 111.12
  • Repeal of New Hampshire's public-works prevailing wage lawRSA Chapter 280 (Minimum Wages of Employees in Public Works), repealed by Laws 1985, 117:1, eff. July 13, 1985
  • State building code adoption (2021 IBC / 2018 IECC)RSA 155-A:1
  • Federal Davis-Bacon threshold, HOME program24 CFR Section 92.354
  • Federal Davis-Bacon threshold, CDBG program24 CFR Section 570.603
  • Build America, Buy America ActInfrastructure Investment and Jobs Act, Pub. L. 117-58, Division G (2021)
  • NH Housing Fee Schedule — LIHTC allocation and upfront monitoring feesNH Housing Fee Schedule for Multifamily Housing, effective for applications received on or after February 28, 2024
  • Prevailing wage prevalence in California LIHTC awards (comparative figure)Terner Center, Low-Income Housing Tax Credit Construction Costs: An Analysis of Prevailing Wages, August 2, 2024 (n=859 awards, 2020–2023)

See this phase modeled on your own site

Book a demo and we'll walk through it live, or get a quote for your team.